South Africa: Supreme Court of Appeal

You are here:
SAFLII >>
Databases >>
South Africa: Supreme Court of Appeal >>
1993 >>
[1993] ZASCA 109
| Noteup
| LawCite
D J Development CC and Others v Arnold (491/92) [1993] ZASCA 109 (6 September 1993)
Download original files |
Case No 491/92
IN THE SUPREME COURT OF SOUTH AFRICA APPELLATE DIVISION
In the matter between:
D J DEVELOPMENT CC 1st Appellant
D G WILLIAMS-JONES 2nd
Appellant
J P VAN BERGEN 3rd Appellant
and
NEIL ANDREW ARNOLD Respondent
CORAM: VAN HEERDEN,
SMALBERGER JJA et HOWIE, AJA
HEARD: 23 August 1993
DELIVERED: 6 September 1993
JUDGMENT
HOWIE, AJA
2
HOWIE, AJA
At East London on 1 1 June 1 985 Neil Arnold, who is the
respondent, and David Williams-Jones, the second appellant, signed a written
agreement referred to throughout the litigation thus far as "HH1".
Williams-Jones did so as promoter of a close corporation to be
formed. In due
course the corporation came into being under the name D J Development CC. It is
the first appellant. Williams-Jones
and Jesse van Bergen, the third appellant,
were at all relevant times the members of the corporation.
For convenience I shall refer to the individual litigants by their surnames and to D J Development CC as "the corporation."
In broad outline the provisions of HH1 were these. Arnold and a corporation named Wild Coast Properties CC would procure the establishment of a company
3
called Club Wildcoast Share Block (Proprietary) Limited ("the share block company"). Arnold would then transfer to the share block company certain coastal land at Haga Haga, near East London, which he was about to acquire. Subject to local government permission the corporation would establish on the land a holiday resort consisting i.a. of a series of cabanas. Initially Arnold would be the share block company's sole director and shareholder but subject to the terms and conditions in HH1 he would transfer 10 shares to the corporation for R100 000. In return for the shares the corporation undertook two major obligations. One was to proceed with the construction of the first 10 cabanas. The other - and this is central to the case - was to ensure, at its expense and within a stipulated time, the installation, in respect of the 10 cabanas, of an access road, water and sewerage reticulation, and other infrastructure,
4
"as set out in the plan and specifications
annexed hereto marked 'E'".
The relevant clause (3.12) went on to provide that:
"The said Corporation undertakes to effect the aforesaid improvements to specifications which are acceptable to the appropriate local authorities and/or other Government bodies, and that all improvements mentioned herein will be completed to the satisfaction of the said Arnold."
All the terms and conditions in HH1 were
deemed to be material (clause 3.18).
Clause 3.24 provided that the terms of
the agreement constituted the entire contract between Arnold and the corporation
and that no
"warranties, representations or conditions" not recorded in HH1, and
no variation of it, would be binding unless reduced to writing
and signed by the
parties.
When HH1 was signed the plan and specifications envisaged as annexure "E" were not attached. There was
5
in fact no annexure at all.
Notwithstanding the absence of annexure "E"
the parties thereafter conducted themselves as if there was a binding contract
between
them.
Registration of the corporation occurred in due course under
the name D J Development CC and not Wild Coast Properties CC.
On 23 August
1985 Williams-Jones and van Bergen signed a deed of suretyship purporting to
secure due performance of the corporation's
obligations to Arnold or the share
block company "in terms of an agreement entered into between the parties."
In
addition, the corporation proceeded with work on the cabanas, the road and the
water and sewerage reticulation.
In 1987, at an advanced stage of the work,
Arnold voiced his dissatisfaction with various aspects.
6
Later still, because he considered that his complaints had not been attended
to, Arnold declared that he was cancelling the contract
allegedly existing
between himself and the corporation. He proceeded to sue the appellants in the
East London Circuit Local Division,
maintaining that the corporation had
breached such contract in a number of respects. Williams-Jones and van Bergen
were sued as sureties.
Arnold claimed i.a. an order confirming cancellation and
the return of the shares.
Basic to his claim was the contention that the
contract on which he relied consisted of HH1 or, alternatively, HH1 as orally
supplemented
to embody a substitute term to replace the missing annexure "E" or,
further alternatively, a tacit agreement, the content of which
was essentially
similar to the provisions of HH1 and again incorporated such a substitute
term.
The appellants' defence of the action was,
7
primarily, that without the proposed annexure "E" - which they alleged had
never existed - the agreement in HH1 was inchoate and did
not constitute a
binding contract, that it could not validly be supplemented and that because the
parties all along thought that
HH1 was binding they never intended a tacit
agreement in its stead. In the second place the appellants denied, if there was
a binding
contract, that it had been breached in any way.
The trial Court
(JENNETT J) held that HH1 on its own bound the parties and that the corporation
had committed a breach of contract.
It therefore granted an order confirming
Arnold's cancellation and directing the corporation to return to him the shares
which it
still held in the share block company. Hence this appeal, the leave of
the trial Court having been obtained.
In supplementary heads of argument filed shortly before the hearing of the appeal counsel for the appellants
8
conceded - properly, in my view - that if there had been a binding contract the corporation had breached its obligations in regard to the provision of sewerage reticulation. It was never in dispute that such breach entitled Arnold to the relief granted by the trial Court. In consequence the essential enquiry now is confined to the question whether there was ever a binding contract.
The evidential material in that regard comprises the testimony of Arnold,
Williams-Jones and van Bergen read in the light of various
documentary
exhibits.
Most of the material facts pertinent to the question for decision
were common cause or not really in dispute.
Arnold was the author of the holiday resort scheme. He was a hotelier whose father owned the farm from which the land concerned was later subdivided. Early in 1984 he engaged a team of consultants and secured
9
the interest of a Johannesburg developer. One of the consultants was a firm of quantity surveyors in which Williams-Jones and van Bergen were partners. For the purposes of a feasibility study and also in order to apply for the necessary local government approval of the scheme, Arnold approached specialists i.a. in the fields of civil engineering, water purification and sewerage treatment for advice and quotations. Their respective written responses comprise the documents referred to in the record as HH2, HH4, HH5 and HH6. These, together with various plans and representations accompanied Arnold's application to the relevant authorities, being the Department of Local Government of the Cape Provincial Administration and the Divisional Council of Kaffraria. Of these two bodies the former had the final decision-making power.
In March 1984 the Divisional Council recommended to the Department that the scheme be approved in principle
10
and in October 1984 the Department of Local Government gave its approval
subject to a number of conditions, one of which was that
septic tanks were not
permitted.
Approval having been granted, Arnold then obtained cost estimates.
After considering these and other implications of the initial scheme
he had had
in mind, Arnold decided to sever involvement with the Johannesburg developer, to
embark upon a less ambitious scheme and
to invite Williams-Jones's firm to
consider participating in it not as a consultant but as a co-developer. The
invitation was extended
by letter dated 1 March 1985.
Williams-Jones accepted the invitation and asked van Bergen to view the site to assess the viability of the scheme in the light of their respective . financial resources. Both were keen on acquiring coastal holiday accommodation and if, as Arnold suggested in his overture to Williams-Jones, the firm built the first 10 cabanas for
11
its own account, Williams-Jones and van Bergen could take one for
themselves.
In due course Williams-Jones and van Bergen decided to
participate in the scheme in the form of a close corporation. Arnold's attorney,
one Laurens, drew a draft agreement and submitted it to them. They referred it
to their own attorneys for advice. The latter suggested
a number of amendments,
reference to which will be made presently. On the strength of the indicated
involvement of Williams-Jones
and van Bergen, the parties had informally agreed
in the interim on the employment of a firm of civil engineers, Meyer and
Associates,
to compile tender documents and specifications in respect of the
construction of an access road. Tenderers were to hold a site inspection
on 21
May 1985 and tenders had to be received by noon on 24 May.
The parties had also agreed in the meanwhile upon
12
the continued relevance and application to the scheme of certain site layout
and locality plans which had been drawn at various times
by the architect
originally engaged by Arnold, one Bridge. These were, respectively, exhibits B1,
B2 and B3. In fact, Williams-Jones
himself gave instructions to Bridge to draw
sketch plans of a redesigned cabana unit because van Bergen would not accept the
rondavel-type
which was depicted in the documentation submitted earlier to the
local authorities.
These sketch plans and the site plans, B1, B2 and B3, were
available when, on 23 May 1985, Arnold, Laurens, Williams-Jones and van
Bergen
met to conclude an agreement. During their two to three hour meeting the draft
was discussed, as also the amendments suggested
by the attorneys acting for
Williams-Jones and van Bergen. All such changes were agreed to, as were the
remaining provisions of the
draft. In addition, Arnold, Williams-
13
Jones and van Bergen signed plans B2 and B3. Only Williams-Jones signed B1
but nothing turns on that. Eventually, all concerned parted
on the understanding
that consensus existed on every material aspect and that Laurens would draw a
finalised agreement. What he produced
in due course was HH1.
On 24 May,
tenders for the roadworks were opened. Williams-Jones considered that they were
so far beyond the corporation's means that
he not only rejected Meyer's design
but terminated his services.
On 11 June 1985 one of the tenderers, Rieger' s
Construction, having been invited by Williams-Jones to re-tender, wrote to the
latter
quoting a reduced price.
On the same day, HH1 was signed. It is
appropriate at this point in the chronology to interpose a reference to some
aspects of the
wording of HH1 . The earlier draft was not produced in evidence
but clause 3.8 .
14
of the draft had apparently referred to "plans and
specifications as may
be agreed upon in writing between the
parties over a period of time." The
advice received by
Williams-Jones and van Bergen in a letter from
their
attorneys was that this was not acceptable and that
reference should
rather be made to plans and
specifications which should be attached to the
contract
and initialled by the parties for identification. They
went on to
say that clause 3.9 referred to a diagram but
that it had not been annexed. Their only comment on
clause 3.12, which then ended with a reference to the work
being completed to Arnold's satisfaction, was that
provision should be made for arbitration in the event of a
dispute between Arnold and the corporation.
As re-drawn in HH1, clauses 3.8, 3.9 and 3.12
read as follows:
"3.8 The said Corporation undertakes immediately upon transfer
of the
15
aforesaid shares into the Corporation's name to proceed with the construction of 10 Cabanas, (Units) to be built in accordance with plans which are attached hereto marked "C" and form part of this Agreement.
3.9 The transfer of the aforesaid shares into the said Corporation' s name will entitle the said Corporation to the use of that portion of ground in respect of 10 designated units in accordance with the Use Agreement annexed hereto, which said units are defined in the annexed diagram which is also annexed hereto marked "D".
3.12 The aforesaid Corporation also . undertakes upon transfer of the aforesaid shares into its name to ensure that a proper and acceptable access road, water reticulation service, sewerage reticulation and all other basic infrastructure as set out in the plan and specifications annexed hereto marked "E" will be installed in respect of the first ten units entirely at the expense of the said Corporation within the aforesaid two year period. The said Corporation undertakes to
16
effect the aforesaid improvements to specifications which are acceptable to the appropriate local authorities and/or other Government bodies, and that all improvements mentioned herein will be completed to the satisfaction of the said Arnold. In the event of a dispute arising between the parties in this connection, the parties agree that such dispute will be referred to an independent arbitrator whose decision will become final and binding upon the parties."
Reverting to the relevant events, Bridge wrote to
Williams-Jones on 12 June confirming the
latter's
instruction that the architectural work (apart from
working
drawings of a standard cabana unit) was to be limited to
site layout and locality plans and specifically that
"Site layout indicating services, water and sewerage to common points and arrowed to supply and disposal to detail by others."
On 17 June Williams-Jones accepted Rieger's
reduced quotation for the roadworks and requested that they
be completed within 3 to 4 weeks.
17
Early in July work was commenced by Williams-Jones in respect of the cabanas
and the water and sewerage systems.
On 5 August the Divisional Council
approved all the various working plans submitted for the establishment of the
resort.
On 8 August Rieger's Construction completed work on the road.
The
suretyship, as mentioned earlier, was signed on 23 August.
On 17 December an
addendum to HH1 was signed, recording, in effect, that the corporation had been
registered as D J Development CC
and that this was the entity which had entered
into the agreement HH1 with Arnold.
Next it is necessary to make brief
mention of how matters progressed as regards the water supply and sewerage
18
system. As already stated, work on those aspects began early in July. To obtain water, Williams-Jones at first engaged a borehole driller but in vain. A weir was then built on the river which ran past the resort but seepage under the wall prevented adequate water retention. From then on various other possible water sources were debated between Arnold and Williams-Jones, the former maintaining that the corporation was obliged to build a dam, the latter denying, such liability. That issue was still unresolved when Arnold decided to cancel although water, had, in the meanwhile, been obtained from a source on his father's farm.
As regards sewerage, Williams-Jones proceeded to instal septic tanks claiming that he had been authorised by the Divisional Council to do so. Arnold's eventual reaction was one of acquiescence provided the local
19
authorities did in fact approve. It is common cause, however, and indeed this
is the reason for the concession by appellants' counsel
on the matter of breach
of contract, that the Department of Local Government never did approve.
It
remains, as far as the relevant evidence is concerned, to mention two aspects on
which Arnold's testimony conflicted with that
of Williams-Jones and van Bergen.
The first concerns the question whether, at their meeting on 23 May 1985, the
documents envisaged
as annexure "E" were in existence, available and agreed
upon. Arnold declared that they were. He said they comprised the plan, B3,
and
the documents HH2, HH4, HH5 and HH6. He added that the last four were in fact
read out by Laurens during the discussions and
very definitely agreed to.
The other two witnesses denied these allegations categorically. They said that the quotations contained in
20
the four documents were so high they would have been unable, at those costs,
to agree to enter into the project. Williams-Jones said
that the plan and
specifications envisaged as annexure "E" were not yet in existence at that
juncture and that it was the parties'
common intention that the details of the
work referred to in clause 3.12 of HH1 would only be agreed and documented at a
later stage.
The second area of dispute concerned the matter of septic tanks.
Williams-Jones alleged having told Arnold that the Divisional Council
had given
unqualified consent to this form of sewage disposal. Arnold, on the contrary,
said that Williams-Jones told him that he
was, with the Divisional Council's
consent, installing septic tanks purely as a temporary measure in order to try
to achieve the
earliest possible completion and sale of the first two
cabanas.
The trial Judge recorded that he was unable to
21
accept Williams-Jones's evidence on sewage disposal in its entirety. Some of the latter's conduct during the performance of the work gave rise to "some disquiet" but he had not conveyed "the impression of deliberate untruthfulness in any of his evidence." Arnold had impressed as an honest witness and it was not possible to accept that he had been untruthful in regard to Williams-Jones's alleged statement that septic tanks were merely a temporary measure. In fact, said the Court, Arnold's evidence on this score was supported by van Bergen who claimed that he had been told the same thing by Williams-Jones. No finding was made in regard to van Bergen as a witness or as to the existence or otherwise of the documents sought to be attached as annexure "E".
The trial Court concluded that even if the parties had not agreed upon the plan and specifications referred to in clause 3.12 there nonetheless remained an
22
obligation, expressed in the remainder of that clause, to provide the
required services in accordance with what was acceptable to
the relevant
authorities and that such obligation had been breached.
It is unnecessary for
present purposes to have any further regard to the dispute about what
Williams-Jones said to Arnold concerning
septic tanks. However, in view of the
arguments presented by the appellants' counsel the other disputed evidential
issue remains
to be considered. Counsel contended, firstly, that clause 3.12 of
HH1 was unenforceable by reason of the non-existence of annexure
"E" and as that
clause was essential to the overall contractual scheme its invalidity brought
the entire agreement HH1 down with
it. Secondly, he submitted that as the
parties had throughout the piece regarded HH1 as binding they could never have
had the intention
to enter into any later contract.
23
The first argument gives rise to the factual enquiry whether the documents
contemplated as annexure "E" were available and agreed
upon.
Giving full
weight to the trial Judge's findings that were favourable to Arnold and
critical, albeit mildly so, of Williams-Jones,
it seems to me that Arnold's
evidence as to the missing annexure "E" cannot prevail. The question here is not
whether Arnold was
truthful but whether the evidence of the other two witnesses
can be rejected. Whatever the shortcomings of Williams-Jones, the evidence
of
van Bergen was not found wanting by the trial Court or attacked by Arnold's
counsel on appeal. Van Bergen's evidence fully supports
Williams-Jones on the
present issue.
In addition, Arnold's evidence is open to criticism in a number of respects, all of which, one may accept, are attributable to bona fide reconstruction or
24
rationalisation. In the first place, if the intention was to annex HH2, HH4, HH5 and HH6 it is significant that they were not signed. By contrast, plans B1 , B2 and B3 were available and were intended as annexures. B1 was initialled by Williams-Jones and the other two signed by all. Secondly, there was no reason to incorporate HH6. That document, referring to a road 10,5 m wide, had by then been superseded by the specification in Meyer's tender document which i.a. required a road 4,5 m wide. Thirdly, Bridge' s letter of 12 June 1985, only a day after the signature of HH1, clearly indicates that at least Williams-Jones had up till then contemplated that drawings and specifications relative to the water and sewerage systems were to be compiled in future. It is unlikely he gave such instructions to Bridge if Arnold's evidence is correct. Fourthly, plain B3 could never have been contemplated as the plan referred to in clause 3.12.
25
Other evidence shows that plan B3 was destined to be annexure "C". What is
more, as a contour locality plan it depicts little, if
anything, of importance
to a detailed description of the water and sewage systems. Finally, none of the
documentary evidence contemporaneous
with the period when the work mentioned in
clause 3.12 was begun, or in progress, contains even a hint that that work was
being done,
or required to be done, according to the provisions of any of the
documents which Arnold said were to be included as annexure "E".
Why the
apparent reference to existing documentation was included in clause 3.12 may be
explained, in my view, on the basis that the
formula suggested by
Williams-Jones's attorneys by way of amendment of the draft clause 3.8 (to
provide for the incorporation of
the contents of an existing annexure instead of
leaving it to the parties to come to a future agreement on the
26
topic supposedly covered by the annexure) was adopted in respect of clause
3.8 and then simply repeated uncritically in respect of
clause 3.12.
I
conclude, therefore, that the matter must be decided on the evidence for
appellants that when HH1 was signed no documentation contemplated
in clause 3.12
was in existence.
On that footing, the phrase "as set out in the plan and
specifications annexed hereto marked 'E'" could not possibly serve to prescribe
how the required work was to be done. The purported obligation created by those
words was accordingly unenforceable and void ab initio.
Despite that
invalidity, said appellants' counsel, one could not strike out or ignore the
offending words as to do so would involve
making a contract for the parties. -
That being so, he urged, the invalidity of the phrase in question rendered the
entire paragraph
invalid
27
and, with it, the whole agreement.
In my view, to disregard the
unenforceable provision would not, in this particular instance, involve
re-writing the agreement for
the parties. The residual provisions of clause 3.12
clearly have sufficient exigible content. The corporation was obliged to perform
the required work in a proper and acceptable manner and according to
specifications acceptable to the relevant authorities. That
is what the
agreement said and that is undoubtedly how the signatories saw the position.
Apart from their saying as much in evidence,
it is quite plain that both Arnold
and Williams-Jones were, with the aid of much discussion beforehand, and with
the assistance of
their respective attorneys, prepared to sign HH1 knowing that
there was no annexure "E" and fully aware (on the - factual basis on
which I
have said the matter must be decided) that the plan and specifications mentioned
in
28
clause 3.12 were not yet in existence much less agreed upon. The . absence of
the plan and specifications therefore made no difference
to them. In fact they
disregarded the unenforceable provision even if they were not conscious of its
invalidity.
Their intention to contract without agreement upon, or the
existence, of those documents can also be demonstrated by employing the
"officious bystander" test: Vogel, N.O. v Volkersz 1977(1) SA 537(T) at 549 A-C.
There can be no doubt that the bystander's relevant
question would have elicited
the unanimous answer that the required infrastructure had to be constructed and
installed according
to the relevant authorities' specifications irrespective of
the non-existence of the proposed annexure.
Appellant's counsel sought to suggest that even the residual provisions were, by reason of the uncertainty inherent in the . words "proper and acceptable",
29
unenforceable for vagueness in any event. Assuming in appellants' favour that the necessary foundation for that argument was sufficiently pleaded, it seems to me however that the use of those words does not lead to the incapacitating uncertainty contended for. There was obviously inherent in the situation some measure of choice and flexibility in relation to matters such as the route the road was to take, where piping was to be laid and what purification and reticulation systems were to be installed. In that context "proper" was, in my view, the equivalent of "proper and workmanlike" - a term well-known to the law concerning contracts of locatio conductio operis - and "acceptable" meant at the very least what it was later in the. clause virtually defined to mean, namely, that the local authorities had to approve concept and details.
Moreover, the evidence given by Williams-Jones under cross-examination, makes it abundantly clear that he,
30
like Arnold, knew and understood without any question what the corporation's
obligations under clause 3.12 were and how they were
properly to be
fulfilled.
In the result HH1 constituted an enforceable binding contract
despite the invalidity of the offending portion of clause 3.12 and appellants'
first argument must therefore fail.
That renders it strictly unnecessary to deal with the second but I shall do
so.
I accept for present purposes the submission that if parties perform
under an invalid but supposedly binding contract such performance
per se is
insufficient to show that they intended to conclude a later, tacit contract on
the same terms. Such' performance would
generally be nothing more significant
than conduct consistent with their belief that the first contract was binding.
That belief,
in turn, would in most instances preclude, or render
31
unnecessary, the formation of a further intention to contract: cf Rand
Trading Co Ltd v Lewkewitsch 1908 TS 108
at 114-115.
I shall also assume
for the purposes of the second argument that the invalidity in clause 3.12
rendered the whole of HH1 invalid.
Notwithstanding the force of those
assumptions, the evidence here is that Arnold and Williams-Jones knew that in
the absence of the
envisaged annexure "E" HH1 did not prescribe how the work
referred to in clause 3.12 was to be done. In that knowledge they nonetheless
proceeded with the work on the cabanas. Rieger' s Construction was contractually
engaged to build the road and Williams-Jones and
Arnold took a variety of steps
to achieve the installation of a water supply and sewerage system. The details
of many of these measures
(other than the architectural plans submitted to the
Divisional Council)
32
were not documented as specifications and they were certainly not annexed belatedly by way of addenda to HH1. There was no attempt to act in accordance with what I have called the offending phrase in clause 3.12. In the circumstances, the steps the parties took were obviously aimed at supplementing the terms of HH1 and at furthering contractual ties between them. This must mean that such steps were taken animo contrahendi. Moreover, not only did such intention pertain to the supplementary measures but, as the word supplementary necessarily implies, to the other contractual ties as well. Such other ties could only have been the same provisions as were contained in HH1.
The unavoidable inference, therefore, is that subsequent to 11 June 1985 Arnold and the corporation contracted tacitly, or tacitly and orally, on the same terms as agreed to in HH1, duly supplemented. Furthermore, as all the conduct and events which are relevant in that
33
regard occurred prior to signature of the deed of suretyship, it follows that
the latter must be understood as applying to that contract.
The sole counter
offered by appellants' counsel in this connection was that clause 3.24 forbade
any unwritten variation or additional
term. The answer is that if HH1 was wholly
invalid, as I have assumed for the purposes of the second argument, it was not
capable
in law of variation or supplementation. Once that is so, there is no
question but that the parties' subsequent contract was binding.
For the
reasons given above the appeal is dismissed, with costs, such costs to include
the costs of two counsel.
C T HOWIE, AJA
Van Heerden JA )
Concur
Smalberger JA )