South Africa: Supreme Court of Appeal
You are here: SAFLII >> Databases >> South Africa: Supreme Court of Appeal >> 1984 >> [1984] ZASCA 62 | Noteup | LawCiteFourie v Leong (63/84) [1984] ZASCA 62 (29 May 1984)
Download original files |
380/82
N.v.H.
J S FOURIE / SYDNEY LEONG
MILLER, JA :-
380/82
N.v.H.
IN THE SUPREME COURT OF SOUTH AFRICA
(APPELLATE DIVISION)
In the matter between :
J S
FOURIE Appellant
and
SYDNEY LEONG Respondent
CORAM: MILLER, CILLIé, JJA,
et GROSSKOPF, AJA
HEARD: 21 MAY 1984
DELIVERED: 29 MAY 1984
JUDGMENT
MILLER, JA :_
The respondent successfully sued the
appellant in the Witwatersrand Local
Division for payment
of / .
2 of damages suffered by reason of the appellant's repudiation of a building contract concluded by the parties for the erection of a dwelling for respondent, which repudiation the respondent accepted. In further particulars supplied at the appellant's request, the respondent explained that the damage suffered and claimed by him (R20 130) represented the difference between the contract price of the erection of the dwelling (R27 870) and the "fair and reasonable cost" of procuring the erection of such building (R48 000) after repudiation of the contract by the appellant. The trial Court (PHILIPS, AJ) entered judgment for the respondent in the sum of R17 780, with costs, and granted certain ancillary relief. The appellant appeals against the
whole /
3 whole of the order.
Two main grounds of appeal are relied
on by the appellant: (1) that no valid or enforceable building contract between
the parties
came into being because there was no true "consensus", and (2) that
in any event, the respondent failed to establish the quantum of any
damage he may have suffered. The first of these grounds is startlingly at odds
with the plea filed by the appellant in the
Court a quo; a plea upon
which the parties went to trial and which has at no time been amended. It is
necessary to examine that plea in some
detail.
Paragraph 2 of the plea contains an admission that appellant signed a printed building contract form
and /
4
and handed it to the respondent, and a statement that prior thereto he,
the appellant, had handed to the respondent a written tender
for the erection of
a dwelling on the respondent's land, a copy of which tender was annexed to the
plea. Also annexed to the plea
was a written "memorandum of agreement" between
the appellant as "the contractor" and the respondent as "the owner", duly signed
by both parties. It was alleged in para 2 of the plea that it had at all
relevant times been the common purpose of the parties to
enter into a written
building contract in the event of the respondent accepting the appellant's
written tender and that such contract
would contain a clause to the effect that
the building activities would commence within
sixty /
5 sixty days of acceptance of the tender or of signing of the
building contract. A further allegation in para 2 of the plea was that
as a
result of a common error the standard building contract signed by the appellant
and thereafter handed to the respondent for
signature, did not contain such
clause. In consequence of all this, so it was pleaded, the appellant was
entitled to rectification
of the building contract annexed to the plea so that
such contract would correctly reflect the agreement between the parties.
I
pause here to observe that para 2 of the plea, the essential terms of which I
have just described, if not in express terms then
very clearly by implication
admits the fundamental allegation in the respondent's
particulars /
6
particulars of claim that the parties entered into a building
contract, in terms of which the appellant undertook to erect a dwelling
on the
respondent's property for an agreed price. The unequivocal assertion that the
appellant is entitled to rectification of the
building contract annexed to his
plea signifies recognition and acceptance by the appellant that full "consensus"
was reached by
the parties.
In para 2 A of the plea, the appellant pleads
that if the Court should find that he is not entitled to rectification of the
agreement
in the respect mentioned, then no valid or enforceable contract came
into existence, by reason of the absence of consensus concerning
each and every
material term ("iedere en
elke /
7 elke wesenlike term") of the agreement. This para is said to be in the alternative to para 2. But in para 3, after denying that he repudiated the agreement ("die ooreenkoms") and pleading that the agreement fell away ("verval het") the appellant alleged in the alternative that if the building contract did not fall away, as alleged, then during May 1980 the parties verbally agreed to cancellation of their agreement ("dat die boukontrak by wyse van 'n mondelinge ooreenkoms tussen die partye gekanselleer is"). And finally, the plea concludes with a prayer (not in the alternative, but in the light of all that has preceded it) that the agreement be rectified in the respect mentioned earlier and that the respondent's claim be
dismissed / . ...
8
dismissed with costs. To the very end of the
pleading,
therefore, the existence of a building contract
between the
parties is recognized.
That such an agreement was in fact concluded
appears, however, not only
from the pleadings but from
the evidence led on behalf of the respondent. I
do
not think it necessary to refer in detail to the
evidence, which was
reasonably fully described in the
judgment a quo. It is sufficient to say that the
evidence reveals
very clearly that after the signing
of the written contract discussions took
place between
the respondent and representatives of the appellant,
and that there was correspondence, all of which confirms
beyond doubt the
recognition by both parties of an
existing /
9 existing and enforceable building agreement for the
erection by appellant of a dwelling on the respondent's property. There was
clearly consensus regarding the essential terms of the contract. It also emerges
very clearly from such discussions that the appellant
discovered that the price
for which he had agreed to erect the dwelling was inadequate; he was not
prepared to carry out his undertaking
for that price. The respondent, though not
obliged to do so, was prepared to meet the appellant to an extent by accepting
liability
for an increased price but such offer was unacceptable to the
appellant who clearly repudiated the contract by refusing to execute
the work he
had undertaken to do. There was no refutation of respondent's evidence in
those
respects /
10
respects, for the appellant, after unsuccessfully applying for absolution from the instance at the close of the respondent's case, closed his case without giving or leading any evidence at all. The allegations in the plea relating to the falling away of the agreement, or its cancellation by the oral agreement of the parties, therefore remain empty shells and are of no avail. There is no substance in the argument that the respondent failed to establish the agreement pleaded by him and it is very clear that the appellant is liable to the respondent for such loss or damage as the latter sustained by reason of the appellant's repudiation of the agreement. This brings me, then, to the second of the grounds upon which it was contended on behalf of the appellant
that /
11
that the respondent ought to have been non-suited,
i.e.,
the ground that respondent failed adequately to
establish the
quantum of his alleged loss or damage.
In the main, the evidence
relied upon for determination of the quantum of the damage suffered by
the respondent was that of Mr Schloss. He is a qualified and registered quantity
surveyor and at the time
of giving evidence was head of the department of
building management in the University of the Witwatersrand and also practised as
a quantity surveyor in a consultant capacity. He was also the editor of a
publication known as the "Builders Pricing Manual". He
was engaged by the
respondent to assess "the fair and reasonable market
cost /
12 cost" of erecting a dwelling such as the appellant had undertaken to erect for the respondent. He explained that in order to arrive at such cost he carried out an inspection of the site, took measurements and prepared a schedule of "all the finishes to the various rooms". He measured the plan of the building on a "rough quantity system" and then priced the quantities required at the average rates pertaining to the building industry at the particular time. He had considerable personal knowledge of the prices of building materials from the exercise of his profession and where he was uncertain he made inquiries in order to establish as nearly as possible the average prices of materials.
He /
13
He prepared a rough bill of quantities consisting
of thirty
pages which was available for inspection
by the appellant and his advisers.
The cost at which
the witness arrived was R46 000 but he
deducted
therefrom the sum of R350 when an error of one metre
in regard to
the length of a wall was brought to his
notice, thus leaving a total sum of
R45 650.
Included in the total sum were provisional sums in
respect of kitchen
cupboards, light fittings and floor
coverings. The items were as taken from
the original
contract and specifications but the prices were taken
at
their "escalated" market cost at the time of his
survey. What were not
included in his total estimate
were professional fees and allied costs, any
special
foundations, excavations in hard or soft rock and
municipal /
14
municipal fees.
The appellant's main criticism of the
evidence of Schloss was that he had not made his cost determination strictly
upon the basis
of the original specifications. The respondent had engaged other
contractors to build the desired dwelling for him and such dwelling
was said to
have differed in certain respects from the dwelling which was the subject of the
building contract and specifications
signed by the parties. Schloss admitted in
evidence that there were
"slight modifications" of the original plans and speci=
fications in the house that was later built but said
that when estimating the "fair and reasonable market
cost", which he was engaged to do, he "ignored the
changes" /
15
changes" in the newly-constructed house and based
his
estimates on the contract drawing in his possession
and the original
specification and the schedule of
finishes. Such deviations as there might
have been
from the initial specifications or plans were relatively
minor,
and would have no significant bearing on the
costs. And where in the
newly-built house there were
more expensive materials than had originally
been
specified (e.g. Harvey tiles instead of ordinary tiles),
the price of the materials originally specified was
taken into consideration for purposes of estimating the
cost of the dwelling. Schloss also explained that in
arriving at the total cost of construction he had allowed
for a profit-margin for the contractor of between 10%
and /
16
and 15%; i.e., the lower percentage in respect of certain
items and the higher in respect of other items.
I am satisfied that the
evidence of Schloss was more than adequate to enable the Court to make a proper
assessment of the quantum of the damage suffered by the respondent. It
must be remembered that although many of the items going towards the
determination of
the total cost of construction might permit of accurate
calculation (e.g. the quantity and price of materials), there are inevitably
imponderables in the assessment of the total cost, which can at best be
estimated, not minutely calculated. I have in mind, for example,
the duration of
the building operations and how this might be affected by delays in the supply
of materials
or by /
17 or by inclement weather or other factors; the emergence of
unforeseen contingencies in excavations, the encountering of rock, and
so on. It
is noteworthy that such provisional items were not taken into account in the
estimation of final cost. If occasional variations
of the original schedules
might have caused some slight additional cost, this would probably have been
over-compensated by the omission
to take into account at all other provisional
items. But, however that may be, it appears to me that in the light of the
detailed
and unrefuted evidence of Schloss, it cannot be said that the trial
Court was not entitled to accept the determination made by Schloss
and to make
an award accordingly.
The /
18 The appeal is dismissed with costs.
S MILLER JUDGE OF APPEAL
CILLIé JA )
) CONCUR GROSSKOPF, AJA )