South Africa: Eastern Cape High Court, Grahamstown

You are here:
SAFLII >>
Databases >>
South Africa: Eastern Cape High Court, Grahamstown >>
2010 >>
[2010] ZAECGHC 51
| Noteup
| LawCite
Bottcher and Others v Author's Builders Ciskei (Pty) Ltd (CA 314/2009) [2010] ZAECGHC 51 (24 June 2010)
Download original files |
REPORTABLE
IN THE HIGH COURT OF SOUTH AFRICA
(EASTERN
CAPE, GRAHAMSTOWN)
Case No: CA 314/2009
In the matter between:
MELISSA BOTTCHER First
Appellant
EILEEN HELENE DE KLERK Second
Appellant
DERROL LAWRENCE BOTTCHER Third
Appellant
and
ARTHUR’S BUILDERS CISKEI (PTY) LIMITED
Respondent
______________________________________________________________
Coram: Chetty,
Revelas JJ and Van der Linde AJ
Date Heard: 31 May 2010
Date
Delivered: 24 June 2010
Summary: Company – Winding-up by Court – Company unable to pay its debts – Building contract – Employer cancelling contract when contractor ceased building operations – Contractor alleging progress payment unlawfully withheld by mortgagee bank – Employer’s claim against contractor an unliquidated claim for damages based on breach of contract – Employer a contingent or prospective creditor having locus standi to present petition for winding-up of company – Opposition to winding-up application based on several grounds – Contractor contending that it had not contracted with employer – Court rejecting allegations as false – Trial court however accepting contractor’s averments that bank reneging on paying third progress payment – Finding factually incorrect –Contractors reliance on arbitration clause misplaced – Respondent though possessed of assets, commercially insolvent – Appeal allowed
______________________________________________________________
JUDGMENT
______________________________________________________________
Chetty,
J
[1] This is an appeal, with leave of the court below, Tshiki J,
against the dismissal of an application for the provisional liquidation
of the
respondent. The appellants sought a winding-up order on the ground that the
respondent was unable to pay its debts as envisaged
in s 345 (1) (c) of the
Companies Act[1] (the
Act). The application was dismissed with costs hence the present appeal. It
would appear from the judgment that although the
question arose whether the
appellants should properly have proceeded by way of trial action the court
below, correctly in my view,
found that whilst there were disputes of fact, they
were capable of resolution on the papers.
[2] A court’s powers to
grant a winding up order is derived from and defined in s 344 of the Act which,
inter alia, provides in s 344 (f) that a company may be wound up it is
unable to pay its debts as described in s 345 of the Act. S 345 in turn,
under
the rubric, “When company deemed unable to pay its debts, provides
in subsection 1 (c) that a company is deemed to be unable to pay its debts where
it is proved to the satisfaction of the
court that a company is unable to pay
its debts. The applicant has to establish a prima facie case which
is done when, on a consideration of all the affidavits filed, such a prima
facie case has been established on a balance of probabilities. This approach
has consistently been followed since Kalil v Decotex (Pty) Ltd and
Another[2]. The position is
that a provisional winding-up order may be issued when the grounds relied upon
on the applicants’ affidavit,
although disputed in the respondent’s
affidavit, can nonetheless be said to have been established prima facie
in the sense that subject to anything that may emerge at a later hearing of oral
evidence, the applicants’ case appears to
have been established on a
balance of probabilities. As Corbett JA pointed out in
Kalil[3], the
provisional order “. . . does no lasting injustice to the respondent for
he will on the return day generally be given
the opportunity, in a proper case
and where he asks for an order to that effect, to present oral evidence on
disputed issues.”
[3] The application for the winding-up of the
respondent company has its genesis in agreements concluded between the
appellants and
the respondent[4] in
terms of which the former, purchased erf 10739 in a housing development styled
Malibu Heights in King Williams Town from the respondent for the
purchase price of R480 000.00, R150 000.00 being in respect of the plot and the
balance of R330 000.00
in respect of a three bedroom house to be built by the
respondent in terms of a separate building contract concluded between them.
The
building operations duly commenced on schedule during February 2008, progressed
rapidly and by 23 April 2008, 52% completed.
Almost immediately building
operations ground to a halt. The respondent was prevailed upon to complete the
project but to no avail.
Instead recriminations were exchanged between the
parties, attorneys were engaged, and a plethora of correspondence exchanged
which
culminated in the application for the winding-up of the respondent. In the
founding affidavit, the first appellant commenced with
a detailed account of the
development, its progress and the subsequent prolonged period of inactivity. She
detailed the unsuccessful
attempts made, by, not only her, but the other owners
of the plots whose homes had in similar fashion been partially completed, to
cajole the respondent’s sole director, one Ricardo Flanagan
(Flanagan), to fulfil the respondent’s contractual
obligations.
[4] She, – (i) adverted to correspondence directed to
the respondent by her and the other affected parties in the development,
and,
when no reply was forthcoming, the notification to him that the contract had
been cancelled; (ii) outlined the steps taken to
secure the services of another
building contractor to complete the project. In summation she alleged that the
respondent’s
failure to complete the project established prima
facie that it was clearly unable to pay its debts and should accordingly be
wound up. In her replying affidavit, and with reference to
various supporting
affidavits, she sought to elaborate upon her contention that the respondent was
commercially insolvent.
[5] The application for the provisional winding
up of the respondent was resisted on a number of grounds which were elaborated
upon
in the answering affidavit deposed to by Flanagan. The first and
main ground of opposition raised was that the respondent was not the party with
whom the appellants had contracted
but another entity, RAF Development CC
(RAF). It is common cause that Flanagan was the sole director and
member of both the respondent and RAF respectively. The court below
however rejected Flanagan’s evidence that RAF was the contracting
party and on appeal before us Mr. Cole was constrained to accept that he
was bound by such finding.
[6] In his answering affidavit, not content
with merely asserting that the respondent was incorrectly cited, Flanagan
embellished his evidence in order not only to disprove the appellant’s
contentions to the contrary but moreover to show that
the first appellant was
deliberately untruthful. He alleged that she was from the outset aware that
RAF was the building contractor in as much as he had specifically
informed her that it was the building contractor. The court below disbelieved
this entire body of evidence. The corollary of the rejection of this testimony
was that the court below, correctly in my view, concluded
that
Flanagan’s version was fabricated. In my view the judge had more
than sufficient reason for disbelieving Flanagan. The documentary
evidence adduced established quite unequivocally that the respondent had
contracted with the appellants and not
RAF.
[7] The judge,
however, thereafter, quite inexplicably, accepted Flanagan’s
evidence that he was entitled to resile from the contract. The rationale for
this finding is difficult to comprehend. Whilst a trier
of fact is quite
entitled to find that a witness may be believed on one aspect of his/her
evidence but not on others, Flanagan’s evidence concerning his
repudiation of the contract was equally contrived. Although the maxim falsum
in uno, falsum in omnibus is not of application to our jurisprudence, where
it is shown that a witness has been deliberately untruthful on one aspect of his
evidence, the trier of fact may conclude that his evidence on another aspect
cannot safely be relied upon. In rejecting Flanagan’s evidence
concerning the identity of the building contractor, the court correctly
concluded, as I stated, that Flanagan was deliberately untruthful and not
merely mistaken. The remainder of his evidence thus required careful
consideration in order to
determine its veracity. In contending that the
respondent was contractually entitled to cease building operations,
Flanagan relied on clause 8.8 of the contract. It reads as follows -
“Should the Employer without good cause prevent the Contractor from
receiving a draw when it is lawfully due, the Contractor,
without prejudice to
any other rights which it may have in terms if this agreement, or in law, shall
be entitled forthwith to require
the Employer to make immediate payment of the
sum due. Should the Employer fail to make such payment, the Contractor shall be
entitled
to suspend all building operations on the Works and to charge the
Employer for all costs incurred directly or indirectly, as a result
of such
suspension, without prejudice to any other rights as the Contractor may have in
terms of this agreement or in the law.”
[8] The court below
found, as a matter of fact, that the refusal on the part of the mortgagee,
Absa Bank Ltd (Absa) to effect a further progress payment
triggered the operation of clause 8.8 and that the respondent’s failure to
continue with
the building operations did not establish that the respondent was
unable to pay its debts as provided for in s 345 of the Act. This
finding is
factually incorrect. In the answering affidavit, Flanagan meticulously
expounded a formula in terms of which he alleged the respondent would be paid.
He stated that where work had been completed
to slab height the respondent would
be entitled to 11% of the contract price and a further 29% when work had
progressed to roof height
and the walls plastered. He alleged further that a
person, whom he described as a Mr. Demo, and whom he described as a bank
inspector, had duly inspected the site and issued both progress certificates as
per the formula.
[9] He further alleged that the respondent continued the
building operations by erecting the roof, installing the ceilings, and
commencing
with the electrical work and painting and then called for the third
progress payment which Absa refused to honour. It will be gleaned from
the aforegoing précis of Flanagan’s evidence that the
non-payment of the third progress certificate purportedly excused him from
continuing the building operation.
[10] On the respondent’s own
version however, it admitted having received an amount of R167 042, 42. It is
not in issue and
in fact confirmed by annexure “RA4” to the replying
affidavit that such payment was effected on 23 April 2008 by Absa
on the
strength of a progress certificate certified by the valuator and indicating that
52% of the building work had been completed.
Although the first appellant stated
that she thereafter signed a further progress payment certificate presented to
her by Flanagan, no real progress in completing the building operations
in fact ensued. It is not in issue that Mr. Demont Troy Herman,
(Herman) (the Mr. Demo referred to by Flanagan) an
independent valuator, was the person who certified annexure “RA4”.
In his affidavit annexed to the first appellant’s
replying affidavit, he
confirmed having been presented with a further progress payment certificate
signed by the first appellant
but which he refused to certify by virtue of the
lack of any meaningful progress in the building operations.
Flanagan’s evidence that Herman in fact signed the third
progress certificate which he then presented to Absa, is clearly
fabricated.
[11] The respondent’s decision to cease building
operations was premised on Absa’s failure to effect payment of the
third progress certificate of the sum of R82 500, 00. The evidence of
Herman was that he consciously refrained from presenting the certificate
to Absa for two reasons viz. the complete lack of any meaningful progress
and the respondent’s failure to install the infrastructural
services and
in particular, the electrical services. A holistic appraisal of the evidence
ineluctably compels the conclusion that
the respondent’s evidence of a
formula in terms of which payments to it would be effected is contrived and
devoid of all substance.
Mr. Cole, somewhat tentatively, submitted that
Herman’s evidence was introduced only in the first
appellant’s replying affidavit, and should accordingly be treated with a
measure
of circumspection. The submission overlooks the fact that the
introduction of Herman’s evidence in no way seeks to supplement the
appellant’s case. The first notion that payments to the respondent was to
take place
in accordance with a formula was specifically raised in the
respondent’s answering affidavit. Those allegations are inconsistent
with
the first appellant’s averment that the respondent was paid an amount of
R167 042, 42 in respect of a progress payment
certificate, an allegation
admitted by the respondent. Herman’s affidavit not only
substantiates the first appellant’s case that Absa had cogent
reasons for refusing to make a further progress payment but that Absa was
never presented with such a certificate by him. Consequently the court
below’s conclusion that clause 8.8 entitled the
respondent to cease
building operations can accordingly not be sustained.
[12] The court
below furthermore quite erroneously found that the
letter[5] addressed to the appellants
attorneys by the respondent’s attorneys constituted proof that the
respondent’s unwillingness
to continue with the building operations was
directly attributable to Absa’s refusal to effect payment of the
third progress certificate. I have already alluded to the fact that no such
certificate was presented
to Absa and that the cessation of the building
operations was entirely due to the respondent’s inability to perform its
contractual
mandate. In addition the agreement provided for the completion of
the project within six months of the respondent being given possession
of the
site i.e. by the end of August 2009, which had, by then, long since elapsed.
[13] The respondent’s explanation for the lack of progress was as
adverted to earlier, the alleged refusal by the bank to effect
payment of the
third progress certificate. As alluded to hereinbefore, Herman refused to
certify the certificate and it was accordingly never presented to Absa.
The real reason for the delay in recommencing building operations is not
difficult to determine. In terms of the approval for the
development granted by
the Buffalo City Municipality (BCM) the developer was responsible
for all costs pertaining to the provision of infrastructural services. In her
founding affidavit the
first appellant alleged that Absa’s refusal
to effect further payments was directly related to the respondent’s
failure to provide electricity to the individual
units and annexed an e-mail
from Absa to the respondent’s attorney in terms of which
Absa’s position was made pertinently clear – further payments
would only be made on submission of a certificate under the hand of
an engineer
certifying that the electricity had been connected.
[14] It is not in
issue that a cheque payment for the electrical mini substation box was made by
Flanagan at BCM on 8 July 2008 and a further cash payment for the
same amount made four months later on 7 November 2008. The respondent’s
explanation
for the cash payment was that he had stopped payment of the cheque
and it was proffered to negate the inference that the cheque had
been
dishonoured. The averment that the cheque had been stopped and not dishonoured
is further evidence of his disingenuousness.
Why and for what purpose payment of
the cheque should have been stopped was never adverted to. If indeed it was
stopped, which appears
highly unlikely, the only plausible reason would be that
Flanagan knew that it would not be met. The respondent, as the developer,
was, in terms of the BCM approval granted, responsible for the provision
of the infrastructural services. The development was far from complete, the six
month
completion date had long elapsed and the cash payment was only made four
months after the cheque payment. The inescapable inference
is that the cheque
was in fact dishonoured and the cash payment made four months later provides
further corroboration for the appellants’
contention that the respondent
was unable to meet its financial commitments.
[15] As further
corroborative evidence that the delay in completing the building operations was
occasioned by the refusal of Absa
to effect payment to him, the respondent
annexed an unsigned affidavit by an engineer, Mr. Peter Allen
(Allen) in which the latter purported to confirm that the BCM had
given permission for provision of infrastructural services to be completed at
the conclusion of the development. These allegations
were likewise patently
untrue. The first appellant in reply annexed an affidavit from Allen in
which he not only denied making a statement in the terms alleged but moreover
refuted the respondent’s allegations attributed
to him and averred that
the only request directed at the BCM by him was that the formal road
works be completed at the end of the development.
[16] In the
introductory portion of this judgment I identified the appellants’ cause
of action against the respondent as an
unliquidated claim for damages for breach
of contract. Mr. Cole, whilst constrained to accept that in law an
applicant who has a valid claim against a company for damages for beach of
contract
is a contingent or prospective creditor of such company and accordingly
has the requisite locus standi to apply for the winding-up of that
company nonetheless submitted that the appellants had to prove that the
respondent was lawfully
indebted to them.
[17] In the course of this
judgment I found that the respondent’s reliance on Absa’s
failure to effect payment of the third progress payment to be devoid of all
substance and that it did not constitute a breach of
contract. On the contrary
the evidence in my view conclusively established that the respondent breached
its contractual obligations
as a consequence of which the appellants were
obliged to themselves complete the project. To that end the appellants obtained
a written
quotation from another builder to complete the project according to
the original specifications who, arithmetically, calculated that
the costs to
complete the project amounted to R226 922, 22. Although only the quotation was
annexed to the appellants’ founding
affidavit, the author thereof, Mr.
B.P Vermaak deposed to an affidavit annexed to the replying affidavit in
which he confirmed that his quotation represented the fair estimate
of the costs
to complete the building project. In such circumstances it can hardly be
contended that the appellants did not have
a valid monetary claim against the
respondent.
Should the matter have been referred for
Arbitration?
[18] As a further ground of opposition to the relief
sought the respondent sought reliance on clause 14 of the agreement. The clause
is inelegantly drafted, littered with typographical errors and not a model of
clarity. Unedited, it reads as follows -
“Arbitration
If any dispute of difference shall arise between the Employer and the
Contractor, during the progress and before the completion of
the work or after
the termination of the Employment of the Contractor under his contract,
abandonment or breach of the contract,
as to the construction of the contract,
or as to any matter or thing arising there under, or as to the withholding of
any draw to
which the Contractor may be entitled, then an architect, civil
engineer, quantity surveyor or any other professional person involved
in the
building industry appointed by both the parties, shall determine such dispute or
difference by a written decision given to
the Contractor. The said decision
shall be final and binding on all the parties.
The arbitration
shall have the power to disclose, review and revise any certificate, opinion,
decision, requisition or notice and
determine all matters in dispute which shall
be submitted to him, and of which notice shall be given as aforesaid, in the
manner
as if no such certificate, opinion, decision, requisition or notice had
been given. Upon every or such any reference, the costs of
and incidental to the
reference and award shall be in the discretion of the arbitrator, who may
determine the amount thereof, or
direct the same to be taxed between attorney
and client or as between party and party shall be direct by whom and to whom an
in what
manner the same shall be borne and paid.”
The court
below, with reference to clause 14, stated, “In my view, given the fact
that the respondent was in denial of breach of the agreement, the applicants
should have considered its
remedies in terms of the contract”. The
only reasonable inference to draw herefrom is that the court below, as an
additional ground refused the application on
the basis that the clause precluded
the applicants from proceeding in the manner in which they did. The issue
relating to arbitration
was pertinently raised in the respondent’s
opposition to the application and the point vigorously pursued by Mr.
Cole on appeal.
[19] It will be seen that clause 14 refers to
three kinds of disputes or differences which are capable of arbitration at three
different
stages viz., during progress and before completion and after
termination of the contract. The first is where the dispute or difference
between the parties is one “as to the construction of the
contract”. The second is where the dispute or difference is one
“as to any matter or thing arising thereunder” and the third
is where the dispute or difference is “to the withholding of any draw
to which the contractor may be entitled”. The question which arises is
whether the dispute or difference which arose between the parties is one which
falls within
the ambit of clause 14. It clearly does not and it ill behoves the
respondent to contend to the contrary. The dispute does not relate
to the
construction of the contract nor to any thing or matter arising thereunder.
[20] As regards the third scenario the dispute must relate to a draw to
which the contractor was entitled to. Flanagan’s untruthfulness
regarding the third progress payment certificate clearly established that the
respondent was not entitled to any further
draws. Furthermore, prior to the
proceedings being launched the respondent vehemently denied having contracted
with the applicants
alleging that RAF was the contractor. On its own version the
resolution of that dispute was clearly not one which fell within the
ambit of
clause 14 and the respondent’s attempt to do so provides further evidence
of Flanagan’s disingenuousness.
[21] The court below was
further persuaded not to grant the relief sought holding that “on the
papers before Court there is no evidence that the respondent has in fact, in the
course of its business, displayed conduct
which amounts to its inability to pay
its debts”. That finding was, with respect to the learned judge
factually incorrect. The dishonouring of the cheque to the BCM and
failure to pay Dot Kemp Estates the commission to which it was entitled
provides further irrefutable proof that the respondent, notwithstanding being
possessed of
sufficient assets was commercially insolvent. Although the court
below referred to a passage in the judgment of Caney J in Rosenbach &
Co (Pty) Ltd v Singh’s Bazaar (Pty) Ltd
[6] it seems, with respect, to
have misunderstood the import of the judgment as the dismissal of the
application so clearly attests to.
Henochberg[7] correctly
points out that “The mere fact that the value of a company’s
assets may exceed the amount of its liabilities does not preclude a finding
that
the company is unable to pay its debts: such a finding may be made if these
assets are not readily realisable and the company
has no further funds with
which to meet current demands – if, in other words, the company is
“commercially insolvent.” Upon a holistic appraisal of the
evidence adduced the applicants clearly established that the respondent was
unable to pay
its debts.
[22] The appeal must accordingly be allowed. The
order of the court below is set aside and replaced by the following
–
“It is ordered -
That the Respondent Company be and is hereby placed under provisional winding-up order in the hands of the Master of this Court;
That a rule nisi do hereby issue calling upon the Respondent to show cause, if any, to this Court at 10h00 on Thursday the 29th day of July 2010 why the Respondent company should not be placed under final winding-up order in the hands of the Master of this Court;
That service of this order be effected in the following manner:-
by ONE (1) publication in the DISPATCH newspaper;
3.2 by the Sheriff:-
on the Respondent at its registered address;
3.2.2 on the Commissioner of South African Revenue Services, East London.
______________________
D.
CHETTY
JUDGE OF THE HIGH COURT
Revelas, J
I
agree.
______________________
E. REVELAS
JUDGE OF THE
HIGH COURT
Van der Linde, AJ
I
agree.
______________________
H.J VAN DER
LINDE
ACTING JUDGE OF THE HIGH COURT
On behalf of the Appellants: Adv D.J Taljaard
Instructed by Nettletons
118A High
Street
Grahamstown
Ref: Mr Nettleton/Sam
Tel: (046) 622 7149
On behalf of the Respondent: Adv S.H Cole
Instructed by Neville
Borman & Botha
22 Hill Street
Grahamstown
Ref:
Mr. J Powers/René
Tel: (046) 622 7200
[1] Act No. 61 of
1973
[2] 1988 (1) SA 943 (A)at
976E-977J
[3] At
979C
[4] Although the deed of sale
identified the respondent as the seller of the erf Flanagan, its sole
director, attempted to establish that it was not. The answering affidavit is
awash with allegations that from the outset,
RAF Development CC, a close
corporation, Flanagan being the sole member was the contractor, I
interpolate to say that this denial was shown to be demonstrably false in reply,
RAF
only being admitted as a home builder in the register of the National Home
Builders registration council on 23 March
2009.
[5] Annexure
“E”
[6] 1962 (4) SA 593
(D) at p597
[7] Henochberg on the
Companies Act. Vol I p 910