2.3.1
If so state particulars. N/A
DECLARATION
I, the undersigned (Name) R Gouws certify that the information furnished in paragraphs 2.1 to 2.3.1 above is correct. I accept that the principal may act against me
in terms of paragraph 23 of the general conditions of contract should this declaration prove to be false.
……………………….
23.2.05
Signature
Date
Regional General Manger
Millennium Waste Management (Pty) Ltd.
Position
Name of tenderer’
[12]
On 25 May 2005 the appellant instituted an urgent application in the court below for relief
divided into two parts. First, it sought an interdict restraining the department from concluding and implementing a contract with
the consortium, pursuant to the award of the tender. Such interdict was to be in force pending the determination of the review sought
in the second part of the relief. Unbeknown to the appellant the department and the consortium had already entered into a service
level agreement which was concluded on 29 April 2005. The implementation of this agreement commenced on 2 May 2005.
These facts probably influenced the decision not to grant the interdict. The record does not shed light on the issue. Despite the
application having been launched on an urgent basis, the review only came before Prinsloo J for consideration on 2 June 2006.
I return to this point later in the judgment. As indicated above the learned judge dismissed the application with costs.
[13]
There are two issues raised in this appeal. The first issue is whether the disqualification of the appellant’s
tender violated its right to procedural fairness. The second relates to the appropriate remedy in the event of the first issue being
decided in the appellant’s favour. I deal with the disqualification issue first.
[14]
Counsel for both the department and the tender board argued in the court below and this court that the
appellant’s tender was lawfully and properly disqualified. In developing this argument, it was submitted that the terms of
the tender documents relating to administrative compliance were couched in peremptory language which expressly stated that non-compliance
would result in disqualification. Proper signing of the tender documents is one of the terms which if not complied with, it was argued,
led to disqualification. It was not procedurally unfair for the tender committee to disqualify the tender on the basis of the appellant’s
failure to sign, continued the argument, because it was forewarned that such a failure would lead to disqualification. Relying on
the definition of ‘acceptable tender’ in the Preferential Procurement Policy Framework Act 5 of 2000 (the Preferential
Procurement Act), counsel concluded by submitting that the appellant’s tender did not constitute an acceptable tender due to
the failure to sign.
[15]
The department’s argument was upheld by the court below. The learned judge, relying on Minister of Environmental Affairs and Tourism v Pepper Bay Fishing, found that the tender committee lacked authority to condone the appellant’s failure to comply with the peremptory requirements
of the tender.
[16]
I cannot accept the department’s argument. On the assumption that there was a valid delegation
of power from the tender board to Dr Manzini and further to the tender committee, the answer to the question of authority lies in
regulation 5(c) which empowers the tender board to accept tenders even if they fail to comply with tender requirements. In these circumstances reliance on the Pepper Bay Fishing case was misplaced. In that case the issue was whether the chief director to whom the power to grant fishing licences was delegated,
had authority to condone procedural defects in applications for fishing rights submitted to him. On the enquiry relating to the chief
director’s powers Brand JA said (para 31):
‘As a general principle an administrative authority has no inherent power to condone failure to comply with a peremptory requirement.
It only has such power if it has been afforded the discretion to do so…. The Chief Director derives all his (delegated) powers
and authority from the enactment constituted by the general notice. If the general notice therefore affords him no discretion, he
has none. The question whether he had a discretion is therefore entirely dependent on a proper construction of the general notice.’
With this I agree and wish to add that in the present case the tender committee was afforded the necessary discretion by reg 5(c).
Therefore it erred in thinking that it did not possess such power.
[17]
Moreover, our law permits condonation of non-compliance with peremptory requirements in cases where condonation
is not incompatible with public interest and if such condonation is granted by the body in whose benefit the provision was enacted
(SA Eagle Co Ltd v Bavuma). In this case condonation of the appellant’s failure to sign would have served the public interest as it would have facilitated
competition among the tenderers. By condoning the failure the tender committee would have promoted the values of fairness, competitiveness
and cost-effectiveness which are listed in s 217. The appellant had tendered to provide the needed service at a cost of R444 244,43
per month whereas the consortium had quoted and was awarded the tender at the amount of R3 642 257,28 per month.
[18]
I turn to the question whether the appellant’s tender constitutes an acceptable tender as defined
in the Preferential Procurement Act. It defines an acceptable tender as ‘any tender which, in all respects, complies with the
specifications and conditions of tender as set out in the tender document’. When Parliament enacted the Preferential Procurement
Act it was complying with the obligation imposed by s 217 (3) of the Constitution which required that legislation be passed in order
to give effect to the implementation of a procurement policy referred to in s 217 (2). Therefore the definition in the statute must
be construed within the context of the entire s 217 while striving for an interpretation which promotes ‘the spirit, purport
and objects of the Bill of Rights’ as required by s 39 (2) of the Constitution. In Chairperson: Standing Tender Committee and Others v JFE Sapela Electronics (Pty) Ltd and Others Scott JA said (para 14):
‘The definition of “acceptable tender” in the Preferential Act must be construed against the background of the system envisaged
by section 217(1) of the Constitution, namely one which is “fair, equitable, transparent, competitive and cost-effective”.
In other words, whether “the tender in all respects complies with the specifications and conditions set out in the contract
documents” must be judged against these values.’
[19]
In this context the definition of tender cannot be given its wide literal meaning. It certainly cannot
mean that a tender must comply with conditions which are immaterial, unreasonable or unconstitutional. The defect relied on by the
tender committee in this case is the appellant’s failure to sign a duly completed form, in circumstances where it is clear
that the failure was occasioned by an oversight. In determining whether this non-compliance rendered the appellant’s tender
unacceptable, regard must also be had to the purpose of the declaration of interest in relation to the tender process in question.
[20]
Counsel for the department submitted that the purpose of the declaration of interest was to curb corruption.
As the failure to sign may be intentional, so he argued, the possibility existed that a person or persons inside the department had
an interest in the tender of the appellant. A perfunctory perusal of the appellant’s declaration shows that the failure to
sign was inadvertent. Secondly, the tender committee does not say the information furnished by the appellant to the effect that it
had no relationship with the department’s employees (including those linked to the evaluation and adjudication of tenders),
was false. I am unable to appreciate how the signing of the form would have safeguarded against corruption. It seems to me that what
is of paramount importance is the nature of the information furnished and not the signature. As is apparent from the declaration
itself, Mr Rhyno Gouws inserted his name on it as the person who furnished the necessary information. He was thus clearly identified.
If the appellant intended to misrepresent facts, it is unlikely that Gouws would have exposed himself in that fashion. I may add
that he signed the tender on behalf of the tenderer on the very same date which the declaration bears.
[21]
Since the adjudication of tenders constitutes administrative action, of necessity the process must be
conducted in a manner that promotes the administrative justice rights while satisfying the requirements of PAJA (Du Toit v Minister of Transport). Conditions such as the one relied on by the tender committee should not be mechanically applied with no regard to a tenderer’s
constitutional rights. By insisting on disqualifying the appellant’s tender for an innocent omission, the tender committee
acted unreasonably. Its decision in this regard was based on the committee’s error in thinking that the omission amounted to
a failure to comply with a condition envisaged in the Preferential Procurement Act. Consequently, its decision was ‘materially
influenced by an error of law’ contemplated in s 6 (2)(d) of PAJA, one of the grounds of review relied on by the appellant.
Therefore, the tender process followed by the department was inconsistent with PAJA. In the light of this finding, it is not necessary,
in my view, to consider other grounds raised by the appellant. Suffice it to say that they were all based on PAJA and it appears
that the appellant could have succeeded on more than one ground.
[22]
The question of relief remains for consideration. While acknowledging that there was no culpable delay
on the part of the appellant to institute review proceedings, exercising its discretion the court below dismissed the application
with costs. In so doing the court overlooked the provisions of s 8 of PAJA which require that any order granted in matters such as
this be just and equitable. This guideline involves a process of striking a balance between the applicant’s interests on the one hand, and the interests
of the respondents, on the other. It is impermissible for the court to confine itself, as the court below did, to the interests of
the one side only. Furthermore, the section lists a range of remedies from which the court may choose a suitable one upon a consideration
of all relevant facts. The dismissal of the application by the court below does not constitute an appropriate and effective relief
contemplated in s 38 of the Constitution. In view of the court a quo’s error this court is entitled to interfere with the order granted.
[23]
The difficulty that is presented by invalid administrative acts, as pointed out by this court in Oudekraal Estates, is that they often have been acted upon by the time they are brought under review. That difficulty is particularly acute when a decision
is taken to accept a tender. A decision to accept a tender is almost always acted upon immediately by the conclusion of a contract
with the tenderer, and that is often immediately followed by further contracts concluded by the tenderer in executing the contract.
To set aside the decision to accept the tender, with the effect that the contract is rendered void from the outset, can have catastrophic
consequences for an innocent tenderer, and adverse consequences for the public at large in whose interests the administrative body
or official purported to act. Those interests must be carefully weighed against those of the disappointed tenderer if an order is
to be made that is just and equitable.
[24]
In this case there are four identifiable interests that need to be taken into account in exercising that
discretion. In doing so it must be borne in mind that the unfairness here does not lie in the process of inviting tenders. It lies
only in the omission of the appellant’s tender from the process of evaluation. It was accepted in argument before us that the
proper course that will need to be followed if the decision is set aside is not to invite fresh tenders but rather for the tender
board to properly evaluate both tenders and decide which tender, if either, to accept.
[25]
The loss to the appellant from the unfair act was no more than the loss of the opportunity to have its
tender considered. It is by no means clear that its tender would have been accepted or that it will be accepted upon a fresh evaluation.
Even if its tender ought to have been accepted at the outset its loss relates mainly to the profit it would have realised on the
contract. We are not told what that profit might be; it might be modest or even minimal. Against that must be weighed the potential
loss that will be caused if it’s tender is not accepted on reconsideration.
[26]
There is no suggestion that the consortium was complicit in some way in bringing about the exclusion
of the tender – had that been shown it would have been appropriate to set the decision aside for that reason alone –
and it must be accepted that it is an innocent party.
[27]
With effect from 1 May 2005 the consortium became obliged to perform, and has performed, the service
that it tendered, under a contract that was concluded on the terms of its tender with some supplementary formal provisions. On the
strength of that contract it purchased eleven vehicles and other equipment at a cost of about R3.5 million and incurred other costs,
and it hired 35 employees. (It is alleged that they were employed on fixed term contracts.) It also leased premises in Polokwane
upon which to construct a waste treatment plant, which it was obliged to construct within four months. Whether it has constructed
the plant does not appear from the evidence but in view of its contractual obligation it is likely that it has done so. The evidence
does not disclose the cost of constructing the plant. The consortium’s return for providing the service takes the form of a
monthly fee over a period of five years. No doubt the monthly fee has been structured to recover its capital, running costs and a
profit. We do not know whether or to what extent the capital costs will have been recovered if the contract terminates midway through
its term.
[28]
From the point of view of the public serious questions arise if the contract is now terminated. The service
is for the removal and safe disposal of medical waste from all public hospitals in Limpopo province (it seems there are 44). The
removal and disposal of medical waste must be carried out without interruption and the province does not have the capacity to step
in itself if the contract is terminated. No doubt some or other interim measures are capable of being taken but how and at what cost
is uncertain.
[29]
There is one further interest to be brought to account that changes the picture and that is the public
purse. At first sight the price differential between the two tenders is enormous: the consortium provides the service at a fee of
R3 642 257 per month, while the appellant tendered to do so at a monthly fee of R444 244. We are not able to assess why the differential
is so large. It might be that the consortium is profiteering obscenely or it might be that the service offered by the appellant was
materially different and hugely under-priced for what is required. In answer to the appellant’s charge that it is profiteering
the consortium pointed out that an earlier call by the province for tenders elicited only one response, and that its price is in
line with estimates that have been made for a comparable service in Gauteng. There are also at least two elements of the respective
tenders – the volume of material upon which they were priced and the facilities for waste disposal that were proposed –
that at first sight might account for a large portion of the differential. But if the appellant is indeed able to provide the service
at the price that it has offered then the completion of the contract by the consortium even at this stage – 29 months has yet
to expire – will clearly be at enormous unwarranted cost to the public purse that could be avoided if the decision is set aside.
[30]
Whether that cost to the public purse will ever eventuate is at this stage a matter only for speculation.
It is only if the appellant’s tender is now evaluated and found to be acceptable, and the decision to accept the consortium’s
tender is not set aside, that any loss will occur. But if the appellant’s tender were not to be accepted, and the decision
to appoint the consortium has meanwhile been set aside, nothing will have been gained and there is the real prospect that loss and
disruption might occur. At best for the province there is the prospect that the consortium might be willing to resume the contract
or to conclude a fresh contract on the same terms. But it will have no obligation to do either and sound commercial reasons can be
envisaged for why it might decline to do so. The province might even be driven to commence the tender process all over again and
end up contracting at a higher price. Meanwhile there is the potential for the interruption of the collection and disposal of medical
waste throughout the province.
[31]
But all that is speculation at this stage. We simply cannot predict what will occur if the tender is
now set aside and uncertainty is thereby introduced. I do not think we should make an order that creates uncertainty – with
no promise of gain but instead the potential for loss and chaotic disruption – when that can be avoided.
[32]
The effects that I have described can be avoided by an order that requires the tenders to be evaluated,
and sets aside the decision to accept the consortium’s tender only if the appellant’s tender is found to be accepted.
An order to that effect vindicates the appellant’s rights to the full while it prevents the potential for disruption to the
service, and it avoids unwarranted loss to the public purse. It might end up that the consortium suffers loss – that will occur
only if appellant’s tender is accepted and even then commercial considerations that minimise the loss might come into play
– but that is inevitable if we are to accommodate the potential loss to the public purse. It seems to me that such an order
promises no loss to the public purse and an uninterrupted service. And if it turns out that the consortium has indeed been profiteering
excessively and loses the contract as a result, then any loss that it might suffer does not weigh heavily with me. The order envisaged
here maintains a balance between the parties’ conflicting interests while taking into account the public interest.
[33]
The reconsideration of the tenders must, in my view, be carried out by the tender board itself and not
the departmental tender committee and the departmental head. Although the Act permits the board to delegate any of its powers, including
the adjudication of tenders, it is undesirable for it to delegate the latter power to persons or bodies which are neither independent
nor impartial. By conferring the sole power upon the board to procure goods and services for the provincial government, both the
Act and the regulations seek to promote the values of independence and impartiality. The process followed by the tender committee
in this matter shows that it did not only lack the skill necessary for adjudicating tenders but also the understanding of the legislative
prescripts. Furthermore, the chairman of the tender committee incorrectly reported to the departmental head that the consortium’s
tender complied with all requirements when this was not the case. On realising the contradiction in the technical report, he invited
its representatives to a meeting so that they could explain the defects. This is proof of a process which is not ‘fair, equitable,
transparent, competitive and cost-effective’. Section 217 of the Constitution was not the only provision overlooked by the
departmental tender committee.
[34]
In conclusion there is one further matter that needs to be mentioned. It appears that in some cases applicants
for review approach the high court promptly for relief but their cases are not expeditiously heard and as a result by the time the
matter is finally determined, practical problems militating against the setting aside of the challenged decision would have arisen.
Consequently the scope of granting an effective relief to vindicate the infringed rights become drastically reduced. It may help
if the high court, to the extent possible, gives priority to these matters.
[35]
The following order is made:
1.
The appeal is upheld with costs including costs of two counsel. Such costs to be paid by the
first and second respondents jointly and severally.
2.
The order of the court below is set aside and the following is substituted:
‘(a)
The exclusion of the tender of the applicant (Millennium Waste Management), and the consequent decision
to accept the tender of the third respondent (the consortium), are declared to have been invalid.
(b)
The tender board is directed to evaluate the tender that was submitted by Millennium Waste Management
and the tender submitted by the consortium relative to one another and to decide by not later than 15 February 2008, or by such later
date as may be determined by a court before that period expires, which tender ought properly to have been accepted.
(c)
Upon reaching such decision the tender board shall immediately record the decision in writing in
its official records and communicate the decision to the respective attorneys of Millennium Waste Management and the consortium such
that it is received by not later than 3 days after the decision has been made.
(d)
If it is decided that the tender of Millennium Waste Management ought to have been accepted but
only upon conditions then the decision shall be deemed to have been made by the tender board and recorded in its records for the
purposes of paragraph (c) upon receipt by the tender board or its nominated official of written acceptance by Millennium Waste Management
of those conditions.
(e )
If it is decided that the tender of Millennium Waste Management ought to have been accepted –
but only if it is so decided – then the following further orders shall issue upon the last day of the month in which such decision
is recorded in the records of the tender board as envisaged by paras (c) and (d):
(i)
the decision that is the subject of this review is set aside.
(ii)
the consortium shall be entitled to claim all moneys that would properly have been due to it but for
this order on that date and to retain all moneys that were properly paid to it at that date.
(iii)
this order shall not prejudice any claim in law that the consortium might have for losses it might have suffered
in consequence of its tender being accepted and subsequently being set aside.
(f)
If it is decided that the tender of Millennium Waste Management ought properly to have been rejected
then the acceptance of the consortium’s tender will remain extant.
(g)
If notwithstanding the terms of this order no decision has been made by the tender board by the
date referred to in paragraph (b) then an order shall issue on that date in the terms contained in paras (i), (ii) and (iii) above.
(h)
The first and second respondents, jointly and severally, are ordered to pay the costs of the applicant,
including the costs of two counsel.’
__________________
C N JAFTA
JUDGE OF APPEAL
CONCUR:
)
HOWIE P
)
NUGENT JA
)
MAYA JA
)
MHLANTLA AJA
SAFLII:
|
Terms of Use
|
Feedback
URL: http://www.saflii.org/za/cases/ZASCA/2007/165.html