![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
South Africa: Supreme Court of Appeal |
[Database Search] [Name Search] [Recent Decisions] [Noteup] [Help]
Last Updated: 7 December 2004
REPUBLIC OF SOUTH AFRICA
IN THE SUPREME COURT OF APPEAL
OF SOUTH
AFRICA
Reportable
Case Number : 373 /
03
In the matter between
MUTUAL AND
FEDERAL LIMITED APPELLANT
and
RUMDEL
CONSTRUCTION (PTY) LIMITED RESPONDENT
Coram
: HARMS, FARLAM, CONRADIE JJA, PATEL et PONNAN AJJA
Date of hearing : 24 AUGUST
2004
Date of delivery : 21
SEPTEMBER 2004
SUMMARY
Insurance –
contract works damaged by cyclone – insurer's contention rejected that
contractor not liable to repair damage
and hence had no insurable interest in
works – claim not excluded by special exception relating to defective
design of contract
works.
___________________________________________________________________________
J U D G M E N T
___________________________________________________________________________
CONRADIE
JA et PATEL AJA
[1] During the week of 21 to 28 February 1997
tropical cyclone Lizette inundated Nampula Province in Mozambique. Over a long
distance
it severely damaged roads that the respondent (‘the
contractor’) was about to hand over to its employer, the Mozambican
Directorate of National Roads and Bridges (‘the employer’). The
storm damage led to an insurance claim that the appellant
(‘the
insurer’) repudiated. The insurer lost before Gildenhuys J in the
Johannesburg High Court. The court found the
insurer liable and ordered it to
pay to the contractor R2.5m plus whatever value added tax might have been paid
by the contractor.
It is against this award that the insurer, with leave of the
trial court, appeals. The contractor, also with leave, cross-appeals
against
the failure of the trial court to award it interest on this
amount.
[2] The contractor’s claim was made under an insurance
policy in terms of which the insurer indemnified both the contractor
and the
employer in respect of fortuitous physical destruction of or damage to works to
be undertaken by the contractor in these
words:
'THE COMPANY HEREBY AGREES subject to the terms exceptions limits and conditions contained herein or indorsed hereon that if during the Period of Insurance or during any further period in respect of which the Insured shall have paid and the Company shall have accepted the premium required any part of the Property Insured shall be lost destroyed or damaged as referred to in Part 1 hereof...the Company will indemnify the Insured as provided hereinafter.'
Part 1 circumscribes the indemnity:
'The Company will by payment or at its option by repair or reinstatement indemnify the Insured in respect of fortuitous physical loss or destruction of the Property Insured arising from any cause (other than as provided in the General Exceptions or in the Exceptions to this Part contained hereinafter) whilst at the Situation of the Contract.'
[3] The property insured comprised two rural roads in Nampula province, the one from Liupo via Corrane to Nampula and the other from Momo Junction to Nametil. The description of the works in the schedule to the insurance contract is worth recording:
'Contract no. bid 107/0b/94: opening of rural gravel roads and rehabilitation and constructions of bridges in Nampula province'.
[4] The contractor sought an indemnity for the repair costs of
101,88 kilometres of the road works that had sustained storm damage.
The
insurer raises two defences. First it maintains that a proper construction of
the building contract leads to the conclusion
that the contractor was not liable
to repair the roads. It therefore did not have an insurable interest in their
restoration and
could only validly have insured the works up to the extent of
its interest, that is to say, for loss or damage that it was obliged
to make
good at its own expense. Second it maintains that the roads were defectively
designed and that the damage suffered therefore
fell outside the policy
indemnity.
[5] For the first defence the insurer relies on the terms of
the construction contract contained in clauses 10 and 11 thereof:
'10 Contractor’s Risk
10.1 All risks of loss or of damage to physical property and of personal injury and death which arise during and in consequence of the performance of the Contract other than the excepted risks are the responsibility of the Contractor.
11 Employer’s Risk
11.1 The Employer is responsible for the excepted risks which are (a)...the risks of war...,or (b) a cause due solely to the design of the Works, other than the Contractor’s design.'
[6] We assume in favour of the insurer the correctness of its
proposition that the contractor insured only its interest in the works.
On this
assumption it would not be liable to repair damage to the works caused solely by
their design by someone other than the
contractor. The roads were not designed
by the contractor but by the employer. But the damage to the roads was not
caused solely
by their design. The damage was caused by an unusually heavy
downpour. The contractor was therefore responsible for their repair.
Clause 11
was meant to safeguard the contractor against the cost of remedial work to a
defective design by someone other than himself.
To try to invoke it in the
context of an insurer's liability for storm damage is to misconstrue its scope
and purpose.
[7] The insurer's obligation to indemnify in the insurance
policy is subject to the usual general exceptions to liability such as
damage or
loss due to war and confiscation. They do not concern us but special exceptions
4 and 5 to Part 1 do:
'The indemnity expressed in this Part shall not apply to or include
4. Loss destruction or damage due to:-
(a) wear and tear rust mildew or deterioration
(b) insects larvae or vermin of any kind
(c) acts of the Insured or his competent or authorized agent or representative which are contrary to the recognized rules of engineering or to any legislation or regulations issued by an authority
(d) cessation of work whether total or partial
5. (a) repairing replacing reinstating or making good any part of the Property Insured which is defective in material workmanship plan or specification...
(b) re-design improvement betterment or alteration on the occasion of repair replacement or reinstatement of loss or damage
(c) defective design.'
[8] The insurer submits that the word ‘design’ is
used in the policy in relation to the suitability of the roads for their
intended purpose. We would not quarrel with that. The intended purpose of the
project was the emergency opening of roads in Nampula
province. It was intended
that what remained of road links in the province after the civil war should be
rehabilitated. It is common
cause that the roads were low cost, high risk, high
maintenance, low volume, all weather roads the main purpose of which was, in
words borrowed by the insurer’s expert from a CSIR report on that kind of
road in Kwa-Zulu Natal 'to get the people out of
the mud'. The roads were built
according to a design philosophy 'as low as you can go for a public road'
according to one of the
contractor’s experts and were meant to be degraded
by the weather and repaired by regular maintenance.
[9] The
insurer’s expert on road construction repeatedly said that the drainage,
but also other aspects of the construction
such as the wearing layer on the
road, should have been better designed. Much stress was laid on how flood
returns – the statistical
frequency with which a storm of a particular
severity might be expected to recur – ought to have been calculated and
incorporated
in the design. Only then would the design not have been
defective.
[10] In effect the appellant’s argument amounts to this:
that if the respondent hoped to be entitled to an indemnity under the
policy for
storm damage to the works, it was not good enough for it to construct, as it
did, the works to the satisfaction of the
employer: it had to construct the
works to the satisfaction of the insurer.
[11] What standard of design
the insurer demanded before it would pay, did not become clear during the trial.
Its expert criticized
various aspects of the drainage, but did not state to what
standard it should have been designed. He thought that the drainage should
have
been designed to withstand the impact of cyclone Lizette but since we do not
know what the return period of Lizette was that
does not set an ascertainable
design standard. Without having established a standard the insurer could not
maintain that the design
was defective.
[12] Moreover, there is no
suggestion that the insurer did not know the nature of the unsophisticated
contract works it was insuring.
It cannot now as a prerequisite to accepting
liability demand that they should have been of a higher quality than the
employer was
prepared to pay for.
[13] There is no acceptable evidence
that the roads, for what they were, were poorly designed. The employer was
represented on site
by its resident engineer, Mr AJ Kruger. He worked for a
firm of consultants, Provia/Van Wyk and Louw International, engaged by the
employer to supervise the construction of the roads. The project was so
unsophisticated and the funding so restricted that Kruger
himself, guided by the
contract documents, was obliged to design drainage works for the contactor as
the roads progressed. He did
this by directing the installation of drains,
culverts and drifts, using as guidelines his own observations of the topography,
evidence
of previous flood levels and local knowledge of flow patterns and soil
conditions. He did not work to a statistically calculated
flow return period.
There is no suggestion that such information was available for Nampula province,
but even if it had been, technological
advances in road design were largely
irrelevant to the rudimentary drainage structures that were all the employer
could afford.
The contention that the design of the contract works was
defective accordingly fails.
[14] The trial court failed to award the
contractor interest. Such interest was claimed on the damages at the legal rate
of interest
according to law. Since the prayer for interest was not dealt with
in the court’s order the contractor after judgment brought
an application
for supplementation of the order to include the interest.
[15] The trial
court was not at the close of the case addressed on the contractor’s
entitlement to interest but the particulars
of claim clearly accommodated the
payment of mora interest as envisaged by the Prescribed Rate of Interest Act 55
of 1975 and the
claim was not abandoned.
[16] The application was opposed
by the insurer who maintained that the interest claim had been compromised when
the quantum of damages
was agreed between the parties. However, Gildenhuys J
was not willing to amend his order to include an award of interest on the
essential ground that he was functus officio. No doubt in coming to this
conclusion he was mindful of the requirements of Rule 42 of the Uniform Rules of
Court and the common
law exceptions to the well-established rule that once a
court has pronounced a final judgment or order it has itself no authority
to
correct, alter or supplement it (see Firestone South Africa (Pty) Ltd v
Genticuro AG 1977 (4) SA 298 (A) at 306G-308A).
[17] We however are
at large to order interest to run on the amount awarded, although the issue of
interest was not dealt with in
the court a quo, if we are of the view
that the contractor is entitled to it (Kudu Granite Operations (Pty) Ltd v
Caterna Ltd 2003 (5) SA 193 (SCA)). We consider that the probabilities do
not favour the conclusion that the contractor settled the interest
claim.
[18] First, on 31 October 2002, while the contractor’s
counsel was leading the evidence of a Mr McDowell, who had been called
to
establish the quantum of the contractor’s loss, the parties reached a
settlement and agreed the loss at R2 500 000. Insurer’s
counsel informed
the court that in view of the settlement of the quantum it was no longer
necessary to proceed with the evidence
of McDowell. The words used by the
insurer’s counsel were ‘quantum of the total loss suffered by the
plaintiff is R2,5
million’. Although language is not an instrument of
mathematical precision there is no ambiguity in these words. If the quantum
included interest the onus rested on the insurer’s counsel to clarify this
since as a general rule a claim for damages would
attract interest, if not
before then after judgment.
[19] Secondly, this interpretation is
strengthened by the insurer’s counsel informing the court that the
agreement was subject
to the right of the insurer ‘to identify three
components of the total loss, these being damage to and fixing of drains, damage
to and fixing of culverts and washaways, and general damage to the rest of the
road.’ After evidence and arguments were concluded
and judgment reserved,
the insurer's attorney informed the trial judge that the insurer did not
‘intend proceeding with any
apportionment of the settlement amount amongst
the three components of the loss as envisaged in the agreement reached in
court’.
[20] Lastly, that this is what the parties must have
envisaged is further borne out by the fact that after quantum was agreed the
insurer admitted that the contractor had made a formal demand on 14 October
1997. If the interest claim had been compromised it
would have been unnecessary
for the parties to agree on the date of demand. The admission was clearly
sought and made in order to
fix a date from which interest might be considered
to run in accordance with the provisions of section 2A(1) and 2A(2)(a) of the
Prescribed Rate of Interest Act 55 of 1975:
[21] The relevant provisions
of this Act are:
‘1 Interest on a debt to be calculated at a
prescribed rate in certain circumstances
(1) If a debt bears interest and the rate at which the interest is to be calculated is not governed by any other law or by an agreement or a trade custom or in any other manner, such interest shall be calculated at the rate prescribed under subsection (2) as at the time when such interest begins to run, unless a court of law, on the ground of special circumstances relating to that debt, orders otherwise.
.....
2A. Interest on unliquidated debts
(1) Subject to the provisions of this section the amount of every unliquidated debt as determined by a court of law, or an arbitrator or an arbitration tribunal or by agreement between the creditor and the debtor, shall bear interest as contemplated in section 1. (2) (a) Subject to any other agreement between the parties the interest contemplated in subsection (1) shall run from the date on which payment of the debt is claimed by the service on the debtor of a demand or summons, whichever date is earlier.
(b).....’
[22] In terms of the Act the contractor would be entitled to interest on
the sum awarded by the court a quo at the prescribed rate from the date
of summons or from the date of the earlier demand provided that the demand was
in writing and
set out the creditor’s claim ‘in such a manner as to
enable the debtor to reasonably assess the quantum
thereof’.
[23] The letter of demand with its annexure clearly sets
out the loss suffered by the contractor and minutely describes the manner
in
which it was computed. It was on the basis of this letter of demand that the
insurer had earlier made a (wholly inadequate) settlement
offer to the
contractor. It obviously did not then consider that it was unable to assess the
loss and that was also not argued in
this Court. It was not disputed that the
applicable prescribed rate of interest is 15,5% per annum.
[24] 1 The appeal is dismissed with costs, which include the costs of two counsel.
2 The cross appeal succeeds with costs. The order of the trial court is amplified by the insertion therein of a paragraph (bbis) reading:
‘(bbis) interest on the amount of R2 500 000 at the rate of 15,5% per annum is to be paid by the defendant as from 14 October 1997.’
J H CONRADIE
JUDGE OF
APPEAL
C N PATEL
ACTING JUDGE OF APPEAL
CONCURRING:
HARMS JA
FARLAM JA
PONNAN
AJA
SAFLII:
|
Terms of Use
|
Feedback
URL: http://www.saflii.org/za/cases/ZASCA/2004/82.html