SAFLII [Home] [Databases] [WorldLII] [Search] [Feedback]

South Africa: Supreme Court of Appeal

You are here:  SAFLII >> Databases >> South Africa: Supreme Court of Appeal >> 1999 >> [1999] ZASCA 37

[Database Search] [Name Search] [Recent Decisions] [Noteup] [Help]


Minister of Public Works and Land Affairs v Group Five Building Ltd (2) (606/96) [1999] ZASCA 37 (28 May 1999)

THE SUPREME COURT OF APPEAL
OF SOUTH AFRICA

CASE NUMBER: 606/96


In the matter between:

THE MINISTER OF PUBLIC WORKS
AND LAND AFFAIRS APPELLANT

and

GROUP FIVE BUILDING LIMITED RESPONDENT

CORAM: HEFER, NIENABER, MARAIS, SCHUTZ and PLEWMAN JJA

DATE OF HEARING: 13 MAY 1999

DATE OF JUDGMENT: 28 MAY 1999



JUDGMENT










PLEWMAN JA
I have had the benefit of reading the judgment of Schutz JA in this matter. I am, with respect, constrained to a different conclusion for reasons which make it necessary to expand upon the nature of the contract in issue. Construction contracts for the erection of large buildings or the execution of substantial works are normally (and probably necessarily) complex documents. One reason why this is so is that experience has taught that despite every effort to describe the work to be performed with great exactitude construction work entails uncertainties which necessitate that such contracts incorporate provisions which permit the omission of, the addition to, or the variation of the works. In the form with which this appeal is concerned the contract is that classified in our law as locatio conductio operis. Several forms of contract are in common use. Lump sum contracts cater in one way for the apportionment of the risks inherent in construction work. Contracts based on Bills of Quantities do so in another way. The choice between these two forms (and indeed others) will be dictated by what the parties consider desirable in their circumstances. Contract forms for both types have over time been developed on an industry basis such as those prepared and approved by the Institute of South African Architects or the Association of South African Quantity Surveyors and the Building Industries Federation, or in Great Britain a form published by the Royal Institute of British Architects. These documents are the subject matter of the standard text books in this field. They have very similar basic structures. Why they are complex is because of the desire to define the work to be done in such a manner as to reduce the uncertainties as far as possible. As is pointed out in the judgment of Schutz JA, often provision is made for the use of specialist subcontractors. This can add to the complexities. Then too, terms are often included to allow payment to be made to the contractor as the work progresses. This is usually done on the basis of interim valuations and measurements. Control of the standard of the work must then be exercised at the time of the grant of certificates authorising payment. It is with a contract in this general form that this appeal is concerned.
The appellant used its own standard contract forms. The problem which arose related to the employment of a specialist to instal a fire alarm system. It will be convenient to refer to appellant where it is appropriate as “the employer”and the respondent as “the contractor” (or, where the context so requires, “the main contractor”). The parties entered into a contract in July 1986 for the conversion of the old Roeland Street gaol in Cape Town into a building to house the State Archives. The Department of Works’ standard tender and contract forms were those used. The contract, as is always the case with such projects, was constituted by a number of separate documents. These were:

i) A tender.

ii) An acceptance of tender.

iii) A formal contract.

iv) A set of Conditions of Contract.

v) A Bill of Quantities.

vi) Drawings and Specifications.
The structure is familiar. The fact that a multiplicity of documents was to be used called for an order of precedence to be laid down because the standard forms could (and did) lead to a conflict between separate parts thereof. What is fundamental to the case and to the proper construction of the contract is that the contract is a Bill of Quantities contract. It is so described in the standard form used and its provisions clearly take that form. The provision determining the order of precedence is found in the Bill of Quantities (the Bill). It provides:

“Indien daar enige teenstrydighede bestaan tussen hierdie voorbereidsels en die kontrakvoorwaardes (GO 676) geniet eersgenoemde voorrang.”


In short the Bill carries the day in any case where conflicts arise between its provisions and those in any other of the contract documents.
Another feature of the contract is that it makes provision in Section 6 of the Bill for prime cost items and provisional sums. These are the subject of clauses 15(1) and (2) of the conditions of contract. Clause 15(2) is relevant to the dispute. It reads:

“15(2) A provisional sum as indicated in the tender documents for work to be performed by a Nominated Sub-contractor or for material to be supplied and fixed shall be expended at such times and in such amounts in favour of such persons as the Representative/Agent shall direct. Such amounts shall be payable by the Contractor or by the Director-General in terms of 16 (5), 16(6) or 16(7) hereof as the case may be without discount or deduction (accordingly all provisional sums are net). At the settlement of an account the amount expended shall be set against such provisional sum and the balance shall be added to or deducted from the Contract Sum, as the case may be; provided that no deduction shall be made by or on behalf of the Director-General in respect of any damages paid or allowed by any Nominated Sub-contractor to the Contractor, the intention being that the Contractor and not the Director-General shall have the benefit of any such damages. The Schedule Rates providing for profit and attendance on any provisional sum shall be adjusted on a value pro-rata basis.”

The provisional sums are introduced in the Bill by the following provision:

VOORLOPIGE BEDRAE EN BOUERSWERK IN VERBAND DAARMEE (ALLES VOORLOPIG)

Alle voorlopige bedrae is netto en dek voorsiening van materiaal en toerusting en installasie waar van toepassing deur spesialis firmas. Voorlopige bedrae sluit nie bouersafslag in nie, maar die tenderaar mag onder die ‘Profyt’-item toelaat vir profyt soos hy nodig ag.

Die Kontrakteur word verwys na Klousules B7.1 en B7.2 van die ‘VOORBEREIDSELS’ afdeling vir definisies en verstelling van ‘Bediening’.”


I need not quote B7.1 and B7.2 but they do not place any obligation on the contractor to supervise the work of nominated subcontractors. What is more, in paragraphs G, H and I provisional sums are stated in respect of fire alarms and, as I shall show, in fact provide a provisional sum for “Bediening”.
Two features of the contract are important. One is the power of the employer to vary the work by omission, addition or variation. Clause 18(1) provides that “no variations, additions, omissions and substitutions whatsoever by the Director-General shall vitiate this Contract”. This is a provision which can only effectively exist when it is coupled (as it is in this case) with provisions which determine changes in the price where the scope of the work changes. To accommodate this the final price in this contract is determined only after completion of the work.
Although much of what follows is set out in the judgment of my brother Schutz it will also be convenient for me to recount certain facts. After the conclusion of the contract, and clearly in terms of what the parties contemplated, tenders were invited and obtained for the fire alarm installation. As a result the employer appointed a firm KPL-ETSA (Pty) Ltd (the subcontractor) to do this and instructed the contractor (in terms of clauses of the contract to which reference will presently be made) to conclude a contract with the subcontractor to supply the necessary materials and to instal the fire alarm system.
What has given rise to the litigation is the fact that it became clear at some point that the subcontractor was not performing its obligations. In particular it was not installing field wiring as specified. On 2 December 1991 the contractor (after having been instructed to do so by the employer) terminated the subcontract. The subcontract work was at that time incomplete and in part defective.
The sequence of events (upon which some argument was based in this Court) was as follows. On 2 December 1991 the employer wrote to the contractor as follows:

“According to your letter, the nominated subcontractor - Messrs KPL-ETSA (Pty) Ltd - is in default.

...... you are hereby instructed to terminate your contract with KPL-ETSA (Pty) Ltd.

The Department hereby nominates the following subcontractors to complete the work - copies of quotations attached.”


(The names and the estimated value of the work and an estimated completion date as well as the need to carry out the work in phases as required by the employer’s consultants are then set out.)
On 4 December 1991 the contractor wrote to the employer, in relation to the newly nominated subcontractors, declining, for reasons given, to enter into contracts with them. It is unnecessary to deal at any length with this because it is irrelevant to my reasons for differing from Schutz JA. The final outcome was that the employer wrote to the contractor on 9 December 1991:

“The Department is of the view that your refusal to employ the subcontractor’s ... constitutes a breach of contract.

As the matter is one of extreme urgency, the Department has no alternative but to conclude contracts directly with the aforementioned subcontractor. All the Department’s rights as against yourselves are reserved.

You are also required, in terms of clause 16(4)(b) and (c) of the contract, to cede to the Department, forthwith, all your rights against Messrs KPL-ETSA (Pty) Ltd.”

(This letter too featured in an argument before this Court.)
The employer then employed the two replacement subcontractors to remedy and complete the installation. It averred that it had incurred expense exceeding the original subcontract sum in an amount of R755 484,53, mainly because this sum had been unnecessarily paid to the original subcontractor. It claimed this from the contractor and (by way of an instruction to the Quantity Surveyor) deducted it in the final account prepared (in terms of clause 23(4) of the contract conditions). A final account is only prepared when the work is complete.
This was the state of affairs when the litigation commenced. The first area of disagreement related to the deduction in the final certificate of the sum of R755 484,53 and the second to a claim by the contractor for extra remuneration under the contract because (so it was contended) it was given “late instructions” and suffered delays. In the first claim the contractor sought a declarator to the effect that the employer was obliged to bear all the costs related to the employment of the second subcontractors and, in the second claim a declarator that the employer was obliged to compensate the contractor for its losses as a result of other delays and the “late giving of instructions”. The latter claim was dismissed by the court a quo and there is no appeal against that order. An order was also sought requiring the employer to rectify the final account by deleting the deduction therein of the above amount. This is merely consequential relief flowing from the first claim. The plea put all these matters in issue. The employer at some later time (precisely when cannot be determined from the papers) introduced a counter claim for damages in the amount of R755 484,53 on the grounds of an alleged breach by the contractor of the main contract (thereby reintroducing the amount deducted in the final certificate in a different guise).
A number of pre-trial conferences was held to obtain admissions and in an attempt to limit the issues. Thereafter a document called a “Statement of Case” (not taking the form of a Stated Case in terms of the rules of court) and a supplementary document called “Agreed Statement of Issues and Onera” were prepared. It was largely on the basis of the admissions and the contentions and counter contentions in these documents that the trial was conducted. The parties also introduced what were said to be “agreed documents” without their being identified and proved by witnesses. Only a very limited amount of evidence was led and what was led was the subject of an objection to its admissibility. It was however agreed that quantum should stand over. In the end the court a quo was asked to decide the matter on the basis of the admissions to be found in the pleadings and elsewhere, the documents which were common cause, and subject to argument on the objection, the evidence. It is not an unfair comment that the pleadings themselves are anything but models of what they should be and that it is extremely difficult to be certain what was ultimately in issue. What is especially difficult to discern clearly is the basis upon which the damages claimed in the claim in reconvention are said to have arisen. It would seem that the amount claimed represents sums paid to the first subcontractor for work which was duplicated by the second subcontractors. Schutz JA so understood the submission made in this regard and so did I.
Without wishing to sound unduly critical of counsel’s well intended efforts, what they in fact achieved seems to have been the opposite of what they intended. A considerable amount of confusion arose. In order to ensure that this Court dealt only with matters which were truly appealable counsel were required to formulate a statement of the issues on appeal which they did in the form of a draft order - being the order proposed in Schutz JA’s judgment.
The appeal accordingly must be dealt with on the basis of the submissions made and contentions advanced in this Court, in the heads of argument and by counsel in argument.
The arguments revolved around the provisions of clauses 3(1) and 16 of the contract. The foundation stone in appellant’s argument is the contention that the contractor is obliged by the terms of clause 3(1) to deliver (as one would in a sale or a lump sum contract) the complete works which would include the subcontractor’s work. Clause 3(1) reads:

“3(1) The Contractor shall provide everything necessary for the proper execution of the Works, comply with the provisions of the Contract and Orders in Writing and carry out and complete the Works to the satisfaction of the Representative/Agent, who may from time to time issue further or amended Drawing and/or Orders in Writing.”


The contractor’s counsel sought to argue that the subcontract works are not covered by this clause. It was said that as a fact no specification for any subcontract work existed at the time when the contract was concluded. It followed, so it was argued, that the subcontract works were therefore a separate form of works not falling within clause 3(1).
There is no substance in this submission. Subcontract works were clearly within the contemplation of the parties at the time of their concluding the main contract. But what is even more compelling is the fact that the contract not only made specific provision for the engagement of nominated subcontractors but it is specifically designed to permit changes in the works if such are required or desired by the employer. As has been pointed out clause 18(1) states that changes will not vitiate the contract. What finally constitutes the works is only determined at the time of delivery (but, I should add, delivery as provided for in the contract). I agree with Schutz JA’s rejection of this argument.
However a further word is necessary. The appellant’s claim in reconvention is also based on a misconception of the meaning of clause 3(1). Clause 3(1) does not provide (as appellant’s argument suggests) that the State Archive Building is to be handed over to the employer. The object of clause 3(1) is to saddle the contractor firmly with the obligation to execute the work in the manner provided in the contract and to clearly vest control of the manner in which and standard to which the work must be carried out in the Representative/Agent (the “agent”). It is this control which is vital to the operation of the contract. Delivery (in the sense of the pleading) is governed by clause 21. It takes place in stages. There is a “first delivery stage” and a “final delivery stage”. Both are controlled and directed by the agent in terms of certificates to be issued. Delivery is subject to the agent’s opinion as to when (in the case of first delivery) the works are “fit for occupation” and (in the case of final delivery) subject to all defects having been rectified. I will return to this aspect when dealing with appellant’s claim in reconvention. I would only add that Schutz JA also speaks of “delivery under the main contract of a building”. To do so is, with respect, to stray into the concepts of a lump sum contract where such a statement would be true. It may seem a fine point but in my view it is important to keep firmly in mind that the present contract is one for work to be executed. If this is not done relevant provisions which govern the determination of the contractor’s obligations can be misunderstood.
The other clause around which the debate centred was clause 16. Although it is set out in Schutz JA’s judgment, it will be convenient to repeat it in part here. The relevant provisions read:

“16. (1) The Director-General may nominate a sub-contractor to execute work or supply or fix goods and such Sub-contractor shall hereinafter be referred to as a ‘Nominated Sub-contractor’.

16. (2) The fact that the Director-General has nominated a Sub-contractor shall not create privity of contract between the Director-General and such Nominated Sub-contractor.

16. (3) The Contractor shall at any time on being requested to do so by the Director-General enter into a contract with a Nominated Sub-contractor within fourteen days of such request in respect of the work for which he has been nominated, in which contract the Contractor shall, inter alia, secure mutatis mutandis for himself the same rights that the Director-General has in terms of this Contract. If the Contractor satisfies the Director-General in writing that he is unable to enter into such a contract because

16. (3) (a) he has an objection which is acceptable to the Director-General against such Nominated Sub-contractor;

16. (3) (b) a Nominated Sub-contractor declines to enter into a contract with the Contractor whereby he undertakes the obligations set out above; or

16. (3) (c) a Nominated Sub-contractor declines to save harmless (sic) and indemnify the Contractor against any negligence on the part of such Nominated Sub-contractor, his agents, workmen and servants or against any misuse by him or them of any materials or plant being the property of the Contractor and against all claims as aforesaid or any claim under the Workmen’s Compensation Act, 1941, as amended, the Director-General shall be entitled to nominate another Nominated Sub-contractor.

16. (4) The Contractor furthermore undertakes -

16. (4) (a) as against the Director-General, to carry out his obligations to the Nominated Sub-contractor under the Nominated Sub-contract and to co-ordinate the Nominated Sub-contractor’s work and the work under the main contract and to ensure that the Nominated Sub-contractor carries out and completes the work under such sub-contract to the Director-General’s satisfaction;

16. (4) (b) in case of default by the Nominated Sub-contractor, to take steps against the Nominated Sub-contractor similar to those set out in 24 hereof if and as requested to do so by the Director-General or, if requested to do so by the Director-General, to cede to the Director-General any rights that the Contractor may have against such Nominated Sub-contractor arising from such default.”

Contractor’s counsel argued that clause 16 provides a separate regime for nominated subcontractors (at least so I understood him). In my view that proposition is overstated. Clause 16 is clearly interlinked with many other provisions in the contract. What is true, however, is that just as with all other contracts, particular clauses have to be considered in the light of specific problems. For example matters relating to prime cost items must be considered fundamentally in terms of clause 15 and variations in terms of clause 18. In this sense clause 16 is the primary clause to which reference must be had. But of course it must be read in conjunction with other provisions in the contract.
In the case of clause 16 it must also be read in the light of the scheme of the contract as a whole. This is particularly so with clause 16(4)(a). It is in this clause that Schutz JA finds an obligation resting on the contractor to supervise (in the fullest sense) the work of the subcontractor. I, for reasons I give below, believe that the word “ensure” must be read in a much more restricted sense. The scheme of the contract is one in which the work is defined; it is performed under the control of and to the satisfaction of the agent; it is paid for at a unit price on the basis of the amount of such work as has actually been executed and paid for in terms of a system which values and measures monthly what has been satisfactorily completed. In the case of work for which provisional sums are provided in the Bill(be it work to be performed or material to be supplied or fixed) the sums so provided may only be expended at times and in amounts as the agent directs. This is so stated in clause 15(2). What is more is that payments of any amount are made (and can only be made) on a certificate based on the value of the work which has been “satisfactorily executed” in the opinion of the agent. This is so stated in clause 23(2)(b)(i).
While the contractor is obliged to pay for subcontract work the reality is that the subcontract work is not work which the contractor itself executes. In saying this I do not question the fact that there is contractual privity between the main contractor and the subcontractor. But what the reality underscores is that the contractor is only to perform such work in relation to the subcontract as is clearly provided for in the main contract as work he must do. This connotes work described and priced in the Bill. He cannot be asked to do work for which he has not stipulated a price because he and the employer have not agreed thereon. The mechanism provided in the present contract is a common one. In North West Metropolitan Regional Hospital Board v T A Bickerton & Son Ltd [1970] 1 All ER 1039 (HL) it was said by Lord Reid at p 1043 d-e:

“The scheme for nominated sub-contractors is an ingenious method of achieving two objects which at first sight might seem incompatible. The employers want to choose who is to do the prime cost work and to settle the terms on which it is to be done, and at the same time to avoid the hazards and difficulties which might arise if they entered into a contract with the person they have chosen to do the work. The scheme creates a chain of responsibility. Subject to a very limited right to object, the principal contractor is bound to enter into a contract with the employers’ nominee, but it has no concern with the terms of that contract, for those terms are settled by the employers and their nominee. I can find nothing anywhere to indicate that the principal contractor can ever have in any event either the right or the duty to do any of the prime cost work itself. That would, I think, be contrary to the whole purpose of the scheme, and it would be strange if the contractor could have to do work for which it never tendered and at a price which it never agreed.”


The ingenuity and success of the scheme may be a matter for opinion. I myself do not have any enthusiasm for this device but Lord Reid is undoubtedly correct when he says that the contractor is not bound or entitled to do such work. Experience shows that technical persons such as Quantity Surveyors seem, in general, not to experience difficulty with the manner in which the subcontract work is incorporated into the main contract. This no doubt is because they concern themselves with realities, namely, that it is work performed for the employer by a person selected by the employer at a price agreed to by the employer and in terms of a contract dictated by the employer. Lawyers however find the concept of contractual privity more absolute. The result is that courts are left to reconcile the conflicting pieces of paper in accordance with ordinary interpretive aids so as to discern what the true intention of the parties was. One such interpretive guide is that the courts should endeavour to interpret contracts in a manner which will give them business efficacy. To attempt to compel a contractor to do work which he has not priced would hardly do that.
Before dealing further with the construction of clause 16, I should outline appellant’s case in the claim in reconvention. As originally pleaded the employer’s case was that the contractor was obliged by clause 3(1) to deliver the entire work and that the contractor breached “his obligations” (sic) in three respects. In paragraph 5 of the claim the contractor was said (i) to have failed to ensure that KPL-ETSA carried out and completed the work under the contract properly, (ii) to have failed to ensure that KPL-ETSA complied strictly with the conditions of the contract, and (iii) to have failed to enforce compliance by KPL-ETSA with the subcontract. The pleading goes on to make averments as to the consequences of such breaches.
In the course of pre-trial procedures and discussions and at a late stage (the date cannot be determined from the record) a further allegation was added. This is pleaded as para 6 bis. (Why it was added to para 6 (which contains the averments as to the consequences of the breach) is obscure.) However, it reads:

“6 bis By virtue of the defects in the work done by KPL-ETSA as set out above (the contractor) breached clause 3(1) of the Conditions of Contract in that it failed to carry out and complete the works to the satisfaction of the (agent).”


I understood appellant’s counsel to base his argument four square on this proposition. The pleadings as a whole, however, reveal a curious situation. In the particulars of claim it is alleged:

“10. The Works as defined in the contract including the fire detection and protection services and carbon dioxide installation, have been completed and handed over to the Defendant.”


This allegation is admitted in the plea. A fact admitted in a pleading is eliminated as an issue in any action. Why, in these circumstances, appellant was permitted to introduce paragraph 6 (bis) is not clear. The question of course is how the matter is to be dealt with now. Since I am of the view that the ambit of clause 3(1) has been misconceived (by both parties) it would, I think, be preferable to overlook the technical difficulty which arises and deal with what was argued. In a case where the pleadings seem to have played very little part this ought not to be unduly harsh on the contractor.
The averment in paragraph 6 bis renders the plea circular because one simply comes back to ask in what respect the contractor is said to have failed to carry out and complete the works. This was a question repeatedly put on the contractor’s behalf at the pre-trial stages of the case. At one of the many pre-trial conferences the answer was that clause 16(4)(a) “reiterated the contractor’s obligation to complete and deliver the works and accordingly places the risk of any default on the part of any nominated subcontractor on the contractor”. It is this proposition which must be considered. It turns, it would seem, on the word “ensure” in clause 16(4)(a). I therefore return to consider whether a duty of supervision is imposed by this word. In Schutz JA’s judgment this proposition is considered on the basis that the contractor had to equip himself to supervise the subcontract work. The difficulty with that proposition is that the Bill does not provide that the contractor is to do such work. In fact it defines his duties quite differently as the quotation from the Bill set out above makes clear. In terms of the Bill no duty of supervision of the subcontract works was placed on the contractor. Indeed the section of the Bill listing the provisional items makes it clear that “bediening” of the installation of the fire alarm system was to be by a nominated subcontractor. Items G and I in section 6 under “Brand Alarms” read:

“G. Voorsien die bedrag van R520 000 vir brand alarm installasie.
...

I. Laat toe vir bediening R10 400.”

These are both provisional sums.
If “ensure” is to be construed as imposing a supervisory duty on the contractor there is then a conflict between the Conditions of Contract and the Bill. The Bill would consequently either override the conditions or the word “ensure” would have to be given a different significance in section 16(4)(a). One must also have regard to the realities which the parties would have had in mind. In the nature of things (with works with which the contract is concerned) it would scarcely be expected that someone stand over all the workmen involved and supervise the insertion of every screw or bolt. Common sense tells one that supervision would take the form of periodic inspections and tests. This is precisely what happened: experts were engaged by the employer and defects were picked up. No one at that stage suggested that the contractor was in breach of the contract in not himself having done so. What was required of him is precisely what is provided for in clause 16(4)(b). The subcontractor’s failure amounted to a default and the contractor was instructed to invoke his contractual rights and, if necessary, all that he could then do was to enforce the subcontract by normal civil proceedings and thereby “ensure” that the subcontract work was performed. When it became apparent that the subcontractor was not capable of performing the only other remedy was invoked.
It does not seem to me that clause 16(4)(a) can envisage anything more than this. Its wording is singularly inapposite to convey an intention that the risk of the consequence of any default by the subcontractor fell on the contractor (as the employer’s pleaded contention goes). In my view when clause 16(4) is read in the light of the other provisions of the contract and of the scheme it provides, it means no more than that compliance is to be brought about by means appropriate to the circumstances - that is by normal legal procedures. This does not result as is suggested that the contractor is conducting his business in the courts.
What supports this conclusion is the fact that control of the works is maintained by the agent and that no payments can, if the contract is correctly administered, be made by the agent for defective work. What has not been correctly done must be redone before it can be certified for payment. There is therefore no call for extreme (and unpriced) measures of supervision. It is all in fact taking place in terms of various clauses in the contract.
There are thus several defects in the employer’s case as I have outlined it. Firstly it seeks to recover payments which, on the facts, one must assume had been incorrectly certified. Certification is not the contractor’s obligation. It is the agent’s. The claim in reconvention was misconceived because no breach was established and because the damage arose (or can only have arisen) because payments were incorrectly certified and not from any other cause. Importantly the contractor was not under a duty to supervise the subcontract works in the manner suggested.
There are some additional difficulties. When the contractor sought instructions from the employer as to how to deal with the subcontractor the employer’s response was not to charge the contractor with a failure to provide supervision. Nor was any such allegation made thereafter, not even in cross-examination of Mr Wright the contractor’s director in control of the contract. All that was put to him was “... and I put it to you that the contract was for the construction and delivery of everything that went into this archives (sic) building”. The answer (after an intervention) was - “that’s correct, as defined in the contract”. The matter was left there. The case argued was thus not put to Mr Wright. His evidence was “... our responsibility initially was to elicit from the specialist nominated subcontractor, an indication that his works were ready for inspection and thereafter to solicit that inspection and approval by the consultants. That having been achieved it would be our responsibility to hand over the completed contract to the department”. There was no challenge of this. I accept that to the extent to which the witness may in part of his evidence have purported to construe the contract it was inadmissible. But the point of the quotation is that the case (subsequently) argued was not put. One further piece of evidence also seems to me to answer the criticisms implicit in Schutz JA’s judgment. In cross-examination the terms of a letter written by the contractor at a time before the termination of the subcontract was put to Mr Wright. I quote a portion thereof. “[we] ... have been closely monitoring and expediting the performance of this critical subcontractor ... we believe in this that we and the consultants have gone beyond what could normally be expected. ...” What the purpose of the cross-examination was and why the facts were not investigated in re-examination is not clear to me. But this seems to stand as evidence of strenuous efforts to ensure that the subcontract work was carried out. By contrast the employer led no evidence.
For these reasons I would dismiss the appeal. This renders it unnecessary for me to deal with the arguments based on the cession, alleged breaches surrounding the renomination instructions or prescription though I would state that I am in agreement with Schutz JA on both the issue of the cession and prescription. The order I propose is:
The appeal is dismissed with costs.

C PLEWMAN


SAFLII: | Terms of Use | Feedback
URL: http://www.saflii.org/za/cases/ZASCA/1999/37.html